Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2008 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* ALL WALLS TOPPED OUT |
|
| 02/20/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EXTERIOR & INTERIOR WALLS TOPPED OUT - OK TO GROUT & CAP PROGRESS AREAS |
|
| 02/15/2008 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* RAINED OUT |
|
| 02/13/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST WALL LINTELS AS PER DETAIL #7 @ 10' LEDGER BOLTS IN PLACE, SOUTH WALL @ 9' INTERIOR COLUMN (EAST) @ 4' -- OK TO GROUT PROGRESS AREAS |
|
| 02/08/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CONTINUOUS EXTERIOR CMU WALLS @ 8' TO 12' OK TO GROUT PROGRESS AREAS |
|
| 02/07/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CONTINUOUS CMU WALLS @ 4' -- OK TO GROUT |
|
| 01/31/2008 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* MAIN SLAB AS PER DETAIL #1 PAGE S2.0 |
|
| 01/29/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* STEM WALLS OK TO GROUT |
|
| 01/25/2008 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED |