Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2008 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 04/21/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* REINFORCEMENT STEEL @ CMU 4 EXTERIOR COLUMNS TO 16' RESTROOM BLDG. 4TH LIFT @ WALLS TO 14'9" AND CONTROL ROOM WALLS W/SLAB TIE IN DOWELS & EMBED PLATES TO 9'9" |
|
| 04/16/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* RESTROOM BUILDING ON S/E OF AUDITORIUM CMU WALLS THIRD LIFT FROM 8' TO 12' --- OK TO GROUT |
|
| 04/11/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 7 CMU CANOPY SUPPORT COLUMNS @ SOUTHEAST CORNER OF BUILDING FROM 4'8" TO 8'8" |
|
| 04/10/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* RESTROOM BUILDING ON EAST EXTERIOR FROM 4'8" TO 8'8" OK |
|
| 04/09/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 8 CMU WALL COLUMNS @ SOUTHEAST CORNER OF AUDITORIUM EXTERIOR 1ST LIFT TO 5FT - AND RESTROOM BLDG. CMU WALLS TO 5FT 1ST LIFT |
|
| 04/08/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU WALLS @ RESTROOM BLDG. @ SOUTHEAST CORNER OF AUDITORIUM 1ST LIFT FROM TOP OF STEM TO 4' |
|
| 02/29/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ EAST ENTRY ABOVE STEEL COLUMN J/1 TO 2 -- TOPOUT |
|
| 02/28/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST ENTRY ABOVE STEEL LINE @ J/1 TO 2 FROM 30' TO 36' W/APPROVAL FROM ENGINEER |
|
| 02/26/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST ENTRY ABOVE STEEL COLUMN FROM 24' TO 30' APPROVED BY ENGINEER |
|
| 01/10/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID B/2 TO 3 TOP OUT TO 38'8" |
|
| 01/09/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID B/2 TO 2.8 FROM 30' TO 34' OK TO GROUT |
|
| 01/08/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT @ B/2 TO 2.8 L/3 TO 5, 5/J.8 TO L & J.8/5 TO 5.8 TOW FROM 4' TO 8' AND CORNERS @ 6 & K FROM 0' TO 4' ALSO B/2 TO 2.8 FROM 18'8" TO 24' AND 3/K TO L, L/3 TO 5, 5/J.8 TO L AND J.8/5 TO 5.8 FROM 8' TO 10' AND CORNERS @ 6 & K FROM 4' TO 8' |
|
| 01/02/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID L/3 TO 5, 3/K TO L, & 5/K TO L FROM 0' TO 4' AFFE |
|
| 12/21/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU REINFORCEMENT STEEL AT GRID 1/A TO K-K/1 TO 2 & 2/H TO K LIFT #13 FROM 48' TO 50' TOP OUT |
|
| 12/20/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID A/1 TO 2, 2/A TO C, 1/A TO K , K/1 TO 2, 2/H TO K FROM 46' TO 50' (TOP OUT) |
|
| 12/19/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID 1/A TO K & K/1 TO 2 12TH LIFT 44' TO 48' AND A/1 TO 2 AND 2/A TO D 13TH LIFT T.O.W 46' TO 50' |
|
| 12/18/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ A/2 TO 1 - 2/A TO C & 1/A TO K FROM 47' TO 50' (TOP OUT) |
|
| 12/14/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* E-1 TO H-2 OK TO GROUT TO 44' |
|
| 12/13/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" CMU WALLS @ LINES A/1- 2 @ 40'-44' 1/D TO K/ - K/2 40'-44' LINE 2/H-K @ 36' TO 40' OK TO GROUT PROGRESS AREAS |
|
| 12/12/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" CMU REINFORCEMENT STEEL @ GRID 1/D TO K, K/1 TO 2 AND 2/H TO K LIFT 10 FROM 36' TO 40' |
|
| 12/11/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* RAINED OUT |
|
| 12/10/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED - RAINED OUT |
|
| 12/06/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID A/1 TO 2, 1/A TO C & 2/A TO C --- 10TH LIFT FROM 36' TO 40' |
|
| 12/05/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT 12" CMU STEEL @ GRID 1/A TO K & K/1 TO 2 9TH LIFT FROM 32' TO 36' |
|
| 12/04/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" CMU CMU REINFORCEMENT STEEL @ GRID 1/A TO K - K/1 TO 2 2/H TO K FROM 32' TO 36' AND J/3.4 TO 6 - 6/B TO J & B/3.4 TO 6 TOP OUT |
|
| 12/03/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
| 11/30/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* NO ACCESS - GATE LOCKED |
|
| 11/29/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* RAINED OUT |
|
| 11/28/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES A/1 TO 2 AND 2/A TO C FROM 32' TO 36' AFF |
|
| 11/26/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES A/1 TO 2 - 2/1 TO 2 - B/3.4 TO 6 - 6/B TO H & H/3 TO 6 FROM 28 FOOT TO 32 FOOT A.F.F.E |
|
| 11/21/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINE A/1 TO 2 1/A TO K - K/1 TO 2 FROM 24 FOOT TO 28 FOOT - OK TO GROUT |
|
| 11/20/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* CANCELLED BY CONTRACTOR |
|
| 11/19/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES K/1 TO 2 2/H TO K - B/3 TO 6 & 6/A TO D.5 ABOVE ELEV. 100' OK TO GROUT |
|
| 11/15/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU STEEL REINFORCEMENT @ GRID J/4 TO 6 AND 6/E TO J 7TH LIFT FROM 20' TO 24' |
|
| 11/14/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCING STEEL @ GRIDS 6/B TO C - B/3.4 TO 6 - LIFT 7 FROM 20' TO 24' 1/B TO D.9 LIFT 6 FROM 16' TO 20' AFF -- OK TO GROUT |
|
| 11/13/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU REINFORCING STEEL AT GRID LINES 1/0.9 TO K-K/1 TO 2-A/TO 2 AND LINE 2/A TO C 6TH LIFT-OK TO GROUT |
|
| 11/09/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID 1/C.3 TO K - 5TH LIFT K/1 TO 2 6TH LIFT - J/5.6 TO 6 - 6/H.3 TO J 16 FEET TO 20 FEET |
|
| 11/08/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
| 11/07/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" CMU REINFORCMENT STEEL @ 6/B TO D.1 @ 12 TO 16 FT B/3.5 TO 6 - 2/B.5 TO C.5 @ 16 TO 20 FEET A.F.F.E |
|
| 11/06/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES A/1 TO 2 FROM 16 FOOT TO 20 FOOT AFF |
|
| 11/05/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES 2/A TO C - 14' TO 20' A.F.F.E |
|
| 11/02/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES A/1 TO 2 2/A TO C TO 14 FOOT - 1/A TO D 4TH LIFT & LIN 2/H TO H.75 5TH LIFT |
|
| 11/01/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINE A/1 TO 2 - 2/A TO C 2ND LIFT & 2/H TO H.75 -- 5TH LIFT - OK TO GROUT |
|
| 10/31/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES A/2.5 TO 6 AND 6/A TO B - J/3.5 TO 6 - 6/F TO J 6TH LIFT AND 1/C TO H 4TH LIFT AND COLUMNS |
|
| 10/30/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* GROUTED - AS PER SPECIAL INSPECTION ON THIS DATE PER LEE RAY |
|
| 10/29/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES - A/2.5 TO 6 K/2.5 TO 6 TO FIFTH LIFT & WEST STEP TO FFE |
|
| 10/26/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 8" CMU @ ELEC. DOOR & REAR DOOR - LINE B/2.5 TO 3 2/H TO J - K/1 TO 2 & 1/H TO K 3RD LIFT - LINE 1/A TO G.3 4TH LIFT - CMU WALLS @ .05 TI & A.5 TO E.9 - LINE 6/E TO K B & K/3.5 TO 6 - 2/H TO K 3RD LIFT |
|
| 10/24/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
| 10/22/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* REINFORCEMENT STEEL @ 8" CMU WALLS AT LINE D.5 @ ELECTRICAL ROOM TO TOPOUT & LINE 2/H TO H.5 2ND LIFT |
|
| 10/19/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID 6/B TO K 3RD LIFT K/2.5 TO 6 SECOND LIFT - J/3.5 TO 5.5 & B/2.5 TO 5.5 4TH LIFT |
|
| 10/18/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
| 10/17/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1. MAKEUP ROOM 1 & 2 NORTH WALL THIRD LIFT W/BOLTS AND STRAPS 2. LINE 1 FROM D TO H 2ND LIFT 3. LINE K FROM 1 TO 2 3RD LIFT |
|
| 10/16/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU REINFORCEMENT STEEL @ GRID LINES 6/A TO J B/2.5 TO 6 2ND LIFT TO 8 FOOT 6 INCH |
|
| 10/15/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU WALL REINFORCEMENT @ GRID LINES 1/H TO K, K/1 TO 2, 2ND LIFT TO 8 FOOT AFFE 2/H TO K 1ST LIFT TO 4 FOOT AFFE AND STEM WALL @ K/2 TO 3 TO FFE |
|
| 10/11/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU MASONRY REINFORCEMENT @ GRID LINES 1/A TO K, A/1 TO 2, K/1 TO 2 & L/3 TO 5 & K/5 TO 6 TO 4 FOOT AFFE |
|
| 10/05/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" MASONRY CMU WALL 1ST LIFT REINFORCEMENT STEEL @ GRID LINES 6/D.5 TO F.5 & J/3.4 TO 6 |
|
| 10/04/2007 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* |