Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PRE SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2007 | PLUMBING - PRE SLAB | Approved | IVRS - Inspection :* | |
| 09/14/2007 | PLUMBING - PRE SLAB | Partial Approval | IVRS - Inspection :* GW FROM COL 10-12 AND FS AT COLS E/11 |
|
| 09/11/2007 | PLUMBING - PRE SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/23/2007 | PLUMBING - PRE SLAB | Partial Approval | IVRS - Inspection :* BAKERY & DELI PRE-SLAB PARTIAL OK |
|
| 08/22/2007 | PLUMBING - PRE SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/27/2007 | PLUMBING - PRE SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/26/2007 | PLUMBING - PRE SLAB | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |