Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2007 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 06/04/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK TO GROUT-EXCEPT FOR BATHROOM PLUMBING NEEDS TO BE WRAPED AND INSPECTED BEFORE THEY FILL LOSE CELLS |
|
| 05/29/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) FIRST 48" LIFT OK |
|
| 05/23/2007 | REINFORCED MASONRY PRE-GROUT | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) VERTICAL REBAR REQUIRED EACH SIDE WINDOW AND DOOR JAMBS 2) VERTICAL REBAR TO OVERLAP REBAR PROTRUDING FROM SLAB 3) CANNOT HAVE PLASTIC PLUMBING PIPING EMBEDDED IN MASONRY 4) STOPPED INSPECTION |