Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/09/2014 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 06/01/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* THIS INSPECTION COVERS FOOTINGS IN ACCORDANCE WITH SPECIFIC DETAIL ON SHEET 1/6 AS FOLLOWING FROM SOUTH 3, 4 ROWS HALF FROM EAST TO WEST ROWS 5, 6 COMPLETED |
|
| 05/25/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CAISSON FOOTINGS (4) - SOUTH ROW - OK TO POUR |
|
| 05/24/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* THIS INSPECTION COVERS FOOTING IN ACCORDANCE WITH SPECIFIC DETAIL ON 1/6 SOUTH LINE (BOTH SIDES NORTH & SOUTH) |
|
| 05/23/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* OFFSET FOOTING EXCAVATION, DO NOT PROVIDE CLEARANCE BETWEEN UP COLUMN AND SAIL. |