Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T07CM01134

Parcel: 123030590

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
11/27/2007 REINFORCED MASONRY PRE-GROUT Approved IVRS - Inspection :*
1) ALL WALLS TOPPED OUT OK TO GROUT AND CAP
11/21/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG - SOUTH WALL @ 20' - TOPPED OUT
EAST WALL @ 20'; EAST BLDG - POPOUT @ 20'
OK TO GROUT PROGRESS AREAS
11/19/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG. EAST 1/3 SOUTH WALL @ 16'; EAST WALL @ 16'
COMMON WALL @ MIDDLE & EAST BUILDINGS @ 16'
MIDDLE BLDG - WEST WALL @ 16' OK TO GROUT PROGRESS AREAS
11/15/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BUILDING - SOUTH WALL 14'-18' EXCEPT FOR SE CORNER SECTION - OK TO GROUT PROGRESS AREAS
11/13/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) EAST BLDG POP-OUT AT 12'; MIDDLE BLDG SOUTH WALL MID POINT-EAST; WEST WALL TO S.W. CORNER AT 12' WEST BLDG AT S.E. CORNER AT 12'-OK TO GROUT PROGRESS AREAS
11/09/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG - SOUTH WALL MID-POINT WEST @ 12'
WEST WALL TO SW CORNER @ 8'
WEST BLDG SE CORNER @ 8'
OK TO GROUT PROGRESS AREAS
11/07/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG - SOUTH WALL; WEST CONTROL JOINT TO EAST WRAP-AROUND @ 4'8" OK TO GROUT
10/31/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG - SOUTH WALL @ 4' - OK TO GROUT
10/29/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP EAST BLD OK
10/26/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
WEST BLDG PERIMETER WALLS @ 20' - EXCEPT FOR SE CORNER; MIDDLE BLDG - NORTH WALL @ 18'4"
OK TO GROUT PROGRESS AREAS
10/24/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST BUILDING PERIMETER WALLS @ 18'4" -
EXCEPT SW CORNER - OK TO GROUT
10/22/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
- WEST BUILDING:
PERIMETER WALLS @ 16' - EXCEPT FOR SE CORNER
- MIDDLE BUILDING:
NORTH WALL MID-POINT TO EAST @ 16'
- LINTEL BETWEEN MIDDLE & EAST BLDG @ 16'
- OK TO GROUT PROGRESS AREAS
10/17/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG:
NORTH WALL MID-POINT EAST; EAST WALL @ 12'

EAST BLDG:
PERIMETER WALLS @ 12' (EXCEPT SW CORNER) OK
TO GROUT PROGRESS AREAS
10/12/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG; NORTH WALL (MID-POINT WEST) @ 12'
WEST BLDG. PERIMETER WALLS EXCEPT SE CORNER @ 12'
OK TO GROUT
10/09/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG. MIDPOINT EAST @ 12'
EAST WALL AT 12'
EAST BLDG. PERIMETER WALLS @ 12'
EXCEPT FOR SW CORNER -- OK TO GROUT
10/05/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
MIDDLE BLDG, NORTH WALL (MID.POINT TO WEST WALL) WEST WALL TO SW CORNER @ 8'
WEST BLDG. PERIMETER WALLS @ 8'
EXCEPT FOR SE CORNER
OK TO GROUT PROGRESS AREAS
10/03/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST BLDG, PERIMETER WALLS @ 8' EXCEPT FOR SW CORNER
OK TO GROUT
09/28/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
- WEST BLDG. ALL WALLS EXCEPT SE CORNER @ 4'
- MIDDLE BLDG. MIDPOINT TO WEST, WEST WALL,
EAST WALL @ 4'
- OK TO GROUT PROGRESS AREAS
09/26/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST BUILDING PERIMETER WALLS @ 4'; MIDDLE BUILDING (NORTH WALL - CENTER PORTION TO EAST WALL) @ 4' GROUTED - SPECIAL INSPECTED
08/30/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST BUILDING
STEM WALL @ 24" CONTINUOUS
OK TO GROUT
08/29/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
STEM WALLS - WEST BUILDING & MIDDLE BLDG @ 0"-40"
OK TO GROUT PROGRESS AREAS