Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2007 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* CORRECTIONS HAVE BEEN MADE |
|
| 04/27/2007 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* USE COPPER CONDENSATE WITHIN 6" OF FURNACE VENT REPLACE FLATTENED TRAP REPLACE 3/8" GAS FLEX INSTALL DAMPER & INSULATE SLEEVE |
|
| 04/13/2007 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. INSULATE SHEETMETAL SLEEVES ON TOP OF COIL. SEAL ALL CONNECTIONS. 2. PROVIDE A TRAP ON PRIMARY DRAIN LINE. PVC CANNOT BE WITHIN 6" OF VENT CONNECTOR. PROVIDE AN OVERFLOW SENSOR ON SECONDARY OUTLET. PROVIDE HOSE CLAMPS ON PUMP & TRANSITION TO COPPER. CONNECT OVERFLOW SENSOR ON PUMP. CONNECT POWER TO PUMP. 3. 3/8" I.D X 12" GAS FLEX NOT ADEQUATE FOR 110,000 BTU 4. PROVIDE MIN. 3 SCREWS IN ALL JOINTS OF VENT CONNECTOR. 5. SECURE WATER LINE IN CLOSET 6. VENT ON CONDENSATE DRAIN MUST BE DOWNSTREAM OF TRAP. TERMINATE CONDENSATE WITHIN 6" OF THE GROUND. NO SEWER VENTS. 7. PROVIDE A SEDIMENT TRAP ON GAS LINE AT FURNACE. 8. LOW VOLTAGE WIRE AT CONDENSOR MUST BE PROTECTED USE CONDUIT 9. PROVIDE ROOF JACKS AT LINE SET PENETRATIONS. |