Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T07CM00192
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/16/2008 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* NORTH PARKING LOT DUMPSTER ENCLOSURE |
|
01/15/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
01/14/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
01/11/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REAR DOUBLE SOUTH TRASH ENCLOSURE FOOTING |
|
01/10/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REAR NORTHEAST CORNER SITE WALL FOOTING |
|
01/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTING FOR EAST SIDE DUMPSTER ENCLOSURE |
|
01/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
01/04/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LAST SIX LIGHT POLE BASES IN SOUTH/REAR PARKING LOT |
|
12/31/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LIGHT BASES (6 BASES) F-6,5,3 AND O-F, D, A9 |
|
12/06/2007 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
11/19/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. MAIN ENTRY POPOUT - TOPPED OUT 2. DRIVE THRU PIERS - TOPPED OUT |
|
11/16/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
11/14/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* DOCK RAMP PRE-SLAB & REINFORCING STEEL |
|
11/06/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REINFORCEMENT STEEL @ PHARMACY DRIVE THRU PIERS |
|
11/05/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
11/01/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTING @ GRID F/1.3 TO 2.1 -- OK TO POUR |
|
10/29/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TWO PILASTERS AT NORTH MAIN ENTRY |
|
10/25/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
10/18/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 3-LIGHT POLE BASES IN FRONT EAST PARKING LOT |
|
10/01/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FREEZER SLAB & WALLS AT S/E CORNER |
|
09/28/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TWO LIGHT POLE BASES IN FRONT (NORTH) LOT THAT WERE RE-POURED |
|
09/26/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* STEM WALL REINFORCEMENT @ SOUTH WALL OF DOCK WELL |
|
09/24/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTING/RETAINING WALL REINFORCEMENT @ SOUTH DOCK WELL WALL |
|
09/20/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) NORTH & EAST REINFORCEMENT STEEL AT DOCK WELL WALLS 2) MASONRY WALLS-GRID LINES 1/D TO E-E/1 TO 2-E/4.5 TO 5-5/E TO D TO 4 ? AFF + 5/0 TO B.6 TO 8 FOOT AFF-5/B.6 TO A.1-A-A.1/1 TO 5-1/A TO B.6 TO 12 FOOT AFF |
|
09/11/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/10/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 6 LIGHT POLE BASES IN NORTH/WEST (FRONT) PARKING LOT |
|
09/06/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 9 - F1 COLUMN FOOTINGS AT FOLLOWING GRID LOCATIONS: B/2 - B/3 - B/4 - C/2 - C/3 - C/4 - D/2 - D/3 & D/4 -- OK TO POUR |
|
09/04/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1 - F2 COLUMN FOOTING @ 5/D & F10 FOOTINGS @ 5/C-5/B & 5/A CONTINUOUS FOOTING @ GRIDLINE 5/D.5 TO A.1 |
|
08/30/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. CONTINUOUS FOOTING @ GRID LINE 1/ C TO E 2. COLUMN FOOTING F-2 @ 1-C |
|
08/29/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. CONT. #WF1 WALL FOOTING FROM GRID A/1 TO C/1 FROM A/1 TO A/5 -- OK TO POUR 2. COLUMN FOOTINGS AT C/1 - B/1 - A/1.6 - A/2.3 - A/3.4 & A/4.3 |