Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/07/2007 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 08/24/2007 | ELECTRIC - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) #4 ALUM CONDUCTOR AT 75 PERCENT IS ONLY ALLOWED 65 AMPS PRESENTLY IN A 100 AMP CIRCUIT 2) PLASTIC BUSHING MUST BE INSTALLED PANEL KNOCKOUT FOR MAIN FEED 3) NAIL PROTECTION MUST BE MINIMUM 16 GAUGE 4) MAKE UP CONNECT ALL GROUND WIRES IN ELECTRIC BOXES AND SECURE WITH A MECHANICAL FASTENER |
|
| 08/23/2007 | ELECTRIC - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. NEED TO ADD SUB-PANEL TO PERMIT 2. NEED TO PUT PROTECTION PLATES ON WIRES LESS THAN 1 1/4" FROM EDGE OF STUD NAILERS |