Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T07CM00069
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/28/2008 | ENGINEERING - FINAL | Approved | PER N KALAHAR - SITE NOW MATCHES STAMPED PLAN PROVIDED BY PATRICIA GEHLEN | |
05/02/2008 | ENGINEERING - FINAL | Partial Approval | OKAY TO CONTINUE ON TEMP | |
04/09/2008 | ENGINEERING - FINAL | Partial Approval | SITE STILL UNDER TEMP C OF O WORK APPEARS TO BE COMPLETE | |
02/21/2008 | ENGINEERING - FINAL | Partial Approval | ALL PEDESTRIAN ACCESS MUST BE SEPARATE FROM CONSTRUCTION TRAFFIC-ALL CONSTRUCTION VEHICLES MUST BE IN WORK AREA OR EMPTY LOT TO THE EAST OF SITE TO ALLOW CUSTOMER ACCESS TO THE BANK TALKED TO JIM BURGE RE DOWNSPOUTS- CONTRACTOR TO REMOVE DOWNSPOUTS FROM BUILDING EXCEPT AT EAST AND WEST SIDES OF BUILDING THE DOWNSPOUTS ON WEST SIDE OF BUILDING ARE TO BE SCUPPERED UNDER SIDEWALK |