Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T07CM00016
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2008 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 11/20/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST TO 4" FD-1 BOX OUT FOR CARWASH TRENCH DRAIN |
|
| 11/19/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* INSTALL OF SAND/OIL INTERCEPTOR VENT TO 10' AFF WATER TEST, INSTALL OF 4" FD-1 WITH VENT TO 10' AFF INITIALED ON P2.1C WATER TEST |
|
| 11/18/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST FOR STUB UP FOR TRENCH DRAIN & INSTALL OF (2) 4" FD-1's FOR CARWASH |
|
| 11/14/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 11/13/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/23/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 3" REDLINE ON PAGE P2.1C AT OWNER REQUEST UNDERGROUND WATER TEST OK PENDING REVISED CITY APPROVED PLAN OF THIS |
|
| 10/16/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. 2" STUB UP & OUT AT EQUIPMENT 310 FOR WATER SERVICE TEST OK 2. 10" DDL PER INITIAL WATER TEST UNDERGROUND ONLY OK 3. 8" DDL PER REDLINE & INITIAL WATER TEST UNDERGROUND ONLY OK |
|
| 10/14/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/08/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 6" DDL PER INITIAL WATER TEST P2.1C OK CONTINUATION OF FD-1 PER INITIAL P2.1C WATER TEST OK |
|
| 09/29/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* THIS INSPECTION FOR ELEVATOR SUMP PUMP & DISCHARGE PIPING TO FLOOR SINK PER PLAN AIR TEST OK |
|
| 09/25/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 4" SAND/OIL INTERCEPTOR DRAINAGE PIPING FROM INITIAL P2.1C THRU PER INITIAL P2.1d |
|
| 09/23/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 2" DRAINAGE WITH TEST TO 10' FOR EQUIPMENT 310 FOR WASHER AND FLOOR SINK OK |
|
| 09/22/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 4" RDL AT STAIR #3 UNDERGROUND WATER TEST OK PER INITIAL P2.1d |
|
| 09/19/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* MENS RESTROOM 303, WOMENS 304, JANITOR 305, LOUNGE 302, UNDERGROUND OK |
|
| 02/28/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* INSTALLATION OF GREASE TRAP & EXTRA FLOOR SINK TO SANITARY PER REDLINES PAGE P2.1A WATER TEST OK THIS WILL REQUIRE REVISED CITY APPROVED PLAN AT LATER DATE PRE-SLAB LINE 6 AND H NORTH & WEST |
|
| 02/27/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 4" FROM SOUTHEAST EXTERIOR SANITARY STUB OUT OF BUILDING TO 6" SANITARY PER REDLINE ON SITE WATER TEST OK -- NEED TO SEE TIE IN AT FUTURE AFTER SITE SEWER AUTHORIZATION TO DISCHARGE |
|
| 01/28/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* ADDITION OF 2" DIRECT DRAIN CONNECTION FOR 3-COMP SINK AT REDLINED CAFE 131 --- WATER TEST OK |
|
| 01/25/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* UNDERGROUND FROM EXISTING 4" BUILDING DRAIN FOR REDLINED ADDITION OF CAFE 131 (2) HAND SINKS, (2) FLOOR SINKS, (1) 3-COMP SINK WATER TEST PARTIAL PENDING APPROVED DIRECT DRAIN CONNECTION FOR RAIN DRAIN COLUMN LINE B, C, D OK |
|
| 12/28/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* (4) 8" RAIN DRAINS TESTED FROM 2" BLD. EXTERIOR TO 10' AFF COLUMN LINE 10 OK |
|
| 12/27/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) WATER TEST 4" INTERCEPTOR DRAINAGE FOR SECURE #160 THRU TO 5' BLDG EXTERIOR INCLUDING VENTS 2) WATER TEST 6" SANITARY FOR (2) ? AND FILLER SINK SECURE 110 INCLUDING VENTS TO B' BLDG EXTERIOR |
|
| 12/06/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 2 COPPER FROM ELEVATOR PIT TO 2' WEST OF PHASE 1 STRUCTURE (UNDERGROUND) WATER TEST 2" DRAIN FOR REDLINED SINK AT CAFE 131 OK PENDING REVISED CITY APPROVED PLAN. 4" BUILDING DRAIN FROM EAST EXTERIOR FOR 4" FD-1 & 2" FD WITH VENT TEST TO 8' VENT PIPING CONTINUOUS, TO BE TESTED AT LATER DATE. |
|
| 12/04/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* OPF REPAIR OK |
|
| 11/28/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST UNDERGROUND AT SHOWROOM AREA PAGE P2.18 EXCEPT EDF-1 AT RESTROOM 134 |
|
| 11/09/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* PIPING IN MASONRY WALL ALONG COL. 8 W/TEST TO 10' OK |
|
| 09/24/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* THIS INSPECTION IS FOR TEMPORARY CAPPING OF GAS, WATER, SEWER FOR DEMO OF SITE FOR NEW BUILDING 2 |