Permit: T07CM00016

Parcel: 135084520


Addresses:

7150 E 22ND ST


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T07CM00016

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
03/16/2009 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
FLAG POLE BASE AND CAGE
02/18/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
LAST 7 LIGHT POLE BASES @ N/E NEW CAR DISPLAY LOT
02/12/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 8-LIGHT POLE BASES AT NORTH/EAST NEW CAR DISPLAY LOT PERIMETER-OK TO POUR
01/12/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PERIMETER LOT LIGHT POLE BASES 10 ON WEST SIDE,
5 ON NORTH SIDE & 2 @ BLDG. FRONT
TOTAL OF 17 -- OK TO POUR
01/08/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
8 LIGHT POLE BASES IN FRONT LOT N/W CORNER
10/10/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
REINFORCEMENT STEEL FOR CONCRETE PEDESTALS AT COLUMNS ALONG GRID LINE "G0"
10/06/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CMU WALLS @ STAIRWAY #3 FROM 36'0" TO 40'0" AFFE AND EQUIPMENT ROOM #310 FROM 4'0" TO 8'0" AFFE
10/03/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED PRE-CAST ERACTION @ SOUTH END OF NEW PARKING GARAGE
10/02/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED ERACTION OF PRE-CAST CONCRETE @ SOUTH END OF NEW PARKING GARAGE
10/01/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED PLACEMENT OF PRE-CAST
CONCRETE AT SOUTH END OF NEW PARKING GARAGE -- SPECIAL INSPECTION ACCEPTED
09/30/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED PRE-CAST CONCRETE ERACTION @ SOUTH END OF NEW PARKING GARAGE
09/29/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED PRE-CAST CONCRETE ERACTION @ SOUTH END OF NEW PARKING GARAGE
09/26/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED PROGRESS AT SOUTH END OF PARKING GARAGE
09/25/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED PRE-CAST ERACTION @ NEW PARKING GARAGE SOUTH END
09/24/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED ERACTION OF PRE-CAST @ SOUTH/WEST
CORNER OF PARKING GARAGE AND RAMP
09/23/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CMU WALLS @ STAIR #3 (FOUR SIDES) FROM 4' TO 12' ABOVE
FFE AS PER ENGINEER'S OK
09/22/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PRE-CAST CONCRETE ERACTION @ PARKING GARAGE
EAST SECTIONS 1 THRU 8 & FLOORS 2 THRU 4
COMPLETE SPECIAL INSPECTOR HAS ACCEPTED
09/19/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EAST SECTIONS 7 & 8, 2ND, 3RD & 4TH FLOOR
PRE-CAST T-DECK PANELS - SPECIAL INSPECTED
09/18/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SECTION 6/EAST COLUMNS & T-DECK, SECTION 5/EAST T-DECK,
SECTION 7 & 8 COLUMNS AND END PANELS PRE-CAST ERACTED
09/15/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SECTION 4 AND 5 EAST
SECTION 4 UPRIGHTS AND SECOND LEVEL T-DECK
PRE-CAST ERACTED -- SPECIAL INSPECTION ACCEPTED
09/12/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SECTIONS #2 & #3 PRE-CAST CONCRETE ERACTION
COMPLETE @ SECOND, THIRD AND FOURTH LEVELS,
SPECIAL INSPECTOR ACCEPTED.
09/11/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EAST SECTION 2 & 3 DECK T-PANELS INSTALLED AT
LEVEL 2 THRU 4 AND WEST LEVELS 2 & 3 -
SPECIAL INSPECTOR HAS ACCEPTED
09/10/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
2ND & 3RD SECTIONS ON WEST UPRIGHTS & END PANELS
09/09/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PRE-CAST CONCRETE ERACTION CONTINUES - EAST HALF OF 2ND AND 3RD SECTIONS FROM NORTH TO SOUTH COLUMNS (4) AND 2ND & 3RD FLOOR T-PANELS
09/08/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FIRST FOUR STORY NORTH SECTION ERACTED, SECOND SECTION STARTED - SPECIAL INSPECTION UP TO DATE
09/04/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUED ERACTION OF PRE-CAST CONCRETE
T-PANELS @ SECOND FLOOR DECK - ALONG W/6 CONCRETE COLUMNS ON NORTH END OF PARKING STRUCTURE
09/03/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
STARTED ERACTION OF PRE-CAST CONCRETE AT NEW PARKING GARAGE
09/02/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CANCELED BY CONTRACTOR
08/28/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
RAINED OUT
CONTRACTOR CANCELED
08/25/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
GRADE BEAM STEEL REINFORCEMENT @ GRID LINES G10/GB.5 TO GC.5 AS PER REVISED DRAWING SK-7 & SSK23 & SSK26
08/22/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
GRADE BEAM REINFORCEMENT STEEL @ GRID LINES
GB/G7 TO G9
G9/GB TO GD AND SOUTH OF G9/GB.5 TO GC.5
08/21/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT @ GRADE BEAMS
AT GRID LINES GA/G2.5 TO G8 - GB/G2 TO G3
G3/GA TO GB - G2.5/GA TO GB AND GB/G5 TO G7
08/20/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
08/19/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
GRADE BEAM #4 @ GRID LINES GC/G3 TO G4 AND G4/GC TO GB
GRADE BEAM #3 @ GB.7/GC TO GB.9 AND GB.9/GB.7 TO G4
AND RETAINING WALL FOOTING @ SOUTH SITE WALL LAST
60 L.F OK
08/18/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
08/16/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. 8" X 24" GRADE BEAMS REINFORCEMENT STEEL @ GRID LINES GB/G1 TO G2.5, G1/GB TO GD AND GC/G1 TO GB
2. FOUR CAISSON TOPPER POURS W/ANCHOR BOLTS FOR
PRE-CAST CONCRETE COLUMNS @ GRID GC/G5, G6, G7 & G8
3. FOUR CAISSON TOPPER POURS W/ANCHOR BOLTS FOR STEEL COLUMNS @ GRID GO/GA.7, GB.2, GB.6 AND GC

NOTE: SPECIAL INSPECTIONS COMPLETED
PAID $150.00 FOR AFTER HOURS INSPECTION
CHECK #2505 PAYABLE TO CITY OF TUCSON
CHASE BANK ACCT.#013972757
08/11/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1 - CAISSON @ NORTH OF G4 & WEST ALONG #10 BETWEEN
GC & GC.5 AND 2 CAISSONS ALONG G 9.5 BETWEEN GB.5 AND GC FOR A TOTAL OF 6 CAISSONS. ALL CAISSONS ARE COMPLETE FOR AREAS C AND D
08/08/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
2 CAISSONS @ G/6 - GB & GC
1 CAISSON @ G5/GC
1 CAISSON @ G7/GC
2 CAISSONS @ G9/GB TO GC
AND 2 CAISSONS @ G9/GB TO GC AND
2 CAISSONS @ G9/GB & GC SOUTH
TOTAL OF 8 CAISSONS
08/07/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 2 CASSIONS AT C.4/GB TO GC, 1 CASSION AT G7/GA, 1 CASSION AT G7/GB TOTAL OF 4 CASSIONS AND SOUTH SIDE RETAINING WALL FOOTING FROM PHASE 1 TO WEST END OK TO POUR
08/06/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 7 TOTAL CASSIONS AT GA/GB/G2.5-3 CASSIONS-GB/G5, 1 CASSION GB/G4, 1 CASSION-GC/G4, 1 CASSION AND GA/G5, 1 CASSION PLUS 15 CASSIONS AT AREA C & D
08/05/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
3 CAISSONS @ LINES G/C - G2 & G3 AND GA/G4
AND 2 CAISSONS @ LINES G4/GB TO GB.5 AND G5/GB
08/04/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
7 BUILDING CAISSONS @ AREA "C" - OK TO POUR
08/01/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CANCELED BY CONTRACTOR
05/21/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. FOOTING FROM STORM DRAIN NORTH FOR RAIL FENCE
2. REBAR - CMU WALL FOOTING FROM TRANSFORMER PAD NORTH TO STORM DRAIN
05/16/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
230 L.F OF RETAINING WALL FOOTING FROM S/E CORNER
NORTH -- OK TO POUR
05/15/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EXCAVATION/LAYOUT REBAR- PARTIAL APPROVAL RETAINING WALL FOOTING 100 L F FROM END OF NEW HEADED WEST OK
03/24/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
03/18/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
03/05/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1 SPREAD FOOTING FOR COLUMN @ 3/K.3
02/14/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
8 COLUMN BASES @ GRID LINE 3.5/B TO H & 2/4 TO K
12/26/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) STEM WALL (2) REINFORCEMENT STEEL AT BLDG NORTH PORTALS-OK
12/07/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTING F-#17
STEEL REINFORCEMENT @ LINE "L"/8.4
TO 8 AS PER SHEET S6.1 DETAIL 104
11/28/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT @ GRADE
BEAM FOOTING @ GRID LINES GB #4 @ GC.7/G9 TO G8 -
G9/G.C.7 TO GD - GB #1 @ G8/GC.7 TO GD
G8#2 @ GD/G8 TO G7 AND GB #5 @ GD/G8 TO G9 AND
GD/G6 TO G7
11/26/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT @ FOOTINGS & COLUMN FOOTINGS (10) AT GRID LINE 9/A TO L
11/21/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
TWO CAISSONS @ GD(WEST)/G8 & G9
11/15/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTING STEEL REINFORCEMENT @ GRID LINE 10/A TO L
OK TO POUR
11/13/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTING REINFORCING STEEL AT 1/E AND H
11/09/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTING REINFORCEMENT @ GRID 1.5/B,C,D & E - 1/H,I,J,K
3.5/B,C,D,E,H - 3/H,I,J & K
4/K & L & A.5/5 & 6 & 4.2 - A.2/A.5
11/08/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
WALL FOOTING @ GRID 6/D TO E
E/6 TO 6.6 - 5/F.5 TO H.5 - I/5 TO 5.5 & 4/K TO L AND COLUMN FOOTINGS @ 5/K, I.5, E.5, D.3, B.6 & A.5 & 6/D.3
11/07/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
REINFORCEMENT STEEL FOR FOOTING @ GRID L/8 TO 4
STAIRWELL 6/6.5 - K/L - 8/7.5 - K TO L
11/06/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
9 - CAISSONS @ GRID LINE "GD"/REINFORCEMENT STEEL
11/05/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
REINFORCEMENT STEEL @ ELEVATOR PIT FLOOR AS PER DETAIL S6.1/111 & 112
11/02/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
COLUMN FOOTINGS REINFORCEMENT STEEL @ GRID LINES
7/B,C
E.5, H, 1, J.5 - OK TO POUR
FOOTING @ D.5/7 TO 8 & B/6.5 TO 8 OK
11/01/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTING REINFORCEMENT STEEL @ GRID LINE 8/K TO A & FOOTINGS AND STAIRWELL @ B8 & NINE CAISSONS ALONG GRID LINE A