Permit: T07BU02618


Addresses:

1631 N SWAN RD

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
06/16/2009 GRADING - INTERMEDIATE Approved
02/11/2009 GRADING - INTERMEDIATE Continued RAMP WAS POURED, RAILING WILL BE ADDED LATER.
02/10/2009 GRADING - INTERMEDIATE Continued CHECK H/C RAMP AND SIDEWALK.
02/02/2009 GRADING - INTERMEDIATE Continued PIA AND ROW WORK IN PROGRESS
01/27/2009 GRADING - INTERMEDIATE Continued MEETING ON SITE TO CHECK H/C RAMP AND SIDEWALK.
01/20/2009 GRADING - INTERMEDIATE Partial Approval SITE IS BEING PREPARED FOR PAVING ON THURSDAY
P.I.A. WORK ON SWAN HAS BEGUN.
01/16/2009 GRADING - INTERMEDIATE Correction Required I MET WITH QUAIN QUAIN TO CHECK HANDICAP RAMPS AND SIDEWALK FORMS PRIOR TO POURING CONCRETE.
1. FORM ADJUSTMENT WILL BE NECESSARY TO ELIMINATE TRIP HAZARD.
2. PROVIDE MAXIMUM OF 5% RUNNING SLOPE ON SIDEWALKS 3. PROVIDE 8.33% MAX SLOPE AND 6' LENGTH FOR HANDICAP RAMPS.
4. PROVIDE BOLLARDS IN TRASH ENCLOSURE PER THE GRADING AND DEVELOPMENT PLANS.
01/14/2009 GRADING - INTERMEDIATE Continued BLUE TOP ON AB IS BEING COMPLETED PRIOR TO PAVING
01/05/2009 GRADING - INTERMEDIATE Correction Required I MET WITH QUAIN QUAIN AND DISCUSSED TRASH ENCLOSURE BOLLARDS AND 10'X10' CLEARANCES, ALSO DISCUSSED 8.33% MAX SLOPE ON 6' H/CRAMPS.
12/22/2008 GRADING - INTERMEDIATE Partial Approval Approved site ofr paving and section of 5ft sidewalk along south side of parking area.
12/03/2008 GRADING - INTERMEDIATE Continued 1. WEST SITE WALL FOUNDATION IS UNDER CONSTRUCTION.
2. CONCRETE CURBS HAVE BEEN CONSTRUCTED ON WEST SIDE OF PROJECT. QIAN QIAN SHAO AND DAVE/EAGLE ROCK WERE REMINDED TODAY THAT ASPHALT PARKING AND PAAL WIDTHS ARE MEASURED AT FACE OF CURB FOR ASPHALT WIDTH DIMENSIONS. THIS WAS PREVIOUSLY DISCUSSED AT THE PRE-CON INSPECTION WITH AMERSON SURVEY PRESENT.
SURVEY AT BACK OF CURB MUST ALLOW FOR 1.5" CURB BATTER.
11/04/2008 GRADING - INTERMEDIATE Continued UNDERGROUND UTILITY CONSTRUCTION IN PROGRESS
10/27/2008 GRADING - INTERMEDIATE Continued WATER AND SEWER LINES SHOULD BE COMPLETE IN ONE WEEK, DRY UTILITIES WILL START 10/29/08 AND SHOULD BE COMPLETE IN 2-3 WEEKS.
10/21/2008 GRADING - INTERMEDIATE Continued UNDERGROUND UTILITY CONSTRUCTION IN PROGRESS
10/01/2008 GRADING - INTERMEDIATE Continued UNDERGROUND R/D BASIN INSTALLED AND BACKFILLED. THE CATCH BASIN AND HATCHES NEED TO BE INSTALLED TO PREVENT UN-AUTHORIZED ENTRY.
UNDERGROUND UTILITY CONSTRUCTION WILL BEGIN NEXT WEEK.
I REITERATED TO QUAIN QUAIN THAT THE PAAL MEASUREMENT WOULD BE MEASURED ON THE PAVEMENT, AND THAT AMERSON SURVEY HAD BEEN INFORMED AT THE PRE-CON MEETING.
10/01/2008 GRADING - INTERMEDIATE Continued R/D BASIN INSTALLED, NEEDS CATCH BASIN AND HATCHES INSTALLED TO PREVENT UNAUTHORIZED ENTRY.
CALL FOR INSPECTION WHEN UNDERGROUND UTILITIES ARE COMPLETE.
PAAL MEASURED ON PAVEMENT.