Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T07BU02618
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/16/2009 | GRADING - INTERMEDIATE | Approved | ||
02/11/2009 | GRADING - INTERMEDIATE | Continued | RAMP WAS POURED, RAILING WILL BE ADDED LATER. | |
02/10/2009 | GRADING - INTERMEDIATE | Continued | CHECK H/C RAMP AND SIDEWALK. | |
02/02/2009 | GRADING - INTERMEDIATE | Continued | PIA AND ROW WORK IN PROGRESS | |
01/27/2009 | GRADING - INTERMEDIATE | Continued | MEETING ON SITE TO CHECK H/C RAMP AND SIDEWALK. | |
01/20/2009 | GRADING - INTERMEDIATE | Partial Approval | SITE IS BEING PREPARED FOR PAVING ON THURSDAY P.I.A. WORK ON SWAN HAS BEGUN. |
|
01/16/2009 | GRADING - INTERMEDIATE | Correction Required | I MET WITH QUAIN QUAIN TO CHECK HANDICAP RAMPS AND SIDEWALK FORMS PRIOR TO POURING CONCRETE. 1. FORM ADJUSTMENT WILL BE NECESSARY TO ELIMINATE TRIP HAZARD. 2. PROVIDE MAXIMUM OF 5% RUNNING SLOPE ON SIDEWALKS 3. PROVIDE 8.33% MAX SLOPE AND 6' LENGTH FOR HANDICAP RAMPS. 4. PROVIDE BOLLARDS IN TRASH ENCLOSURE PER THE GRADING AND DEVELOPMENT PLANS. |
|
01/14/2009 | GRADING - INTERMEDIATE | Continued | BLUE TOP ON AB IS BEING COMPLETED PRIOR TO PAVING | |
01/05/2009 | GRADING - INTERMEDIATE | Correction Required | I MET WITH QUAIN QUAIN AND DISCUSSED TRASH ENCLOSURE BOLLARDS AND 10'X10' CLEARANCES, ALSO DISCUSSED 8.33% MAX SLOPE ON 6' H/CRAMPS. | |
12/22/2008 | GRADING - INTERMEDIATE | Partial Approval | Approved site ofr paving and section of 5ft sidewalk along south side of parking area. | |
12/03/2008 | GRADING - INTERMEDIATE | Continued | 1. WEST SITE WALL FOUNDATION IS UNDER CONSTRUCTION. 2. CONCRETE CURBS HAVE BEEN CONSTRUCTED ON WEST SIDE OF PROJECT. QIAN QIAN SHAO AND DAVE/EAGLE ROCK WERE REMINDED TODAY THAT ASPHALT PARKING AND PAAL WIDTHS ARE MEASURED AT FACE OF CURB FOR ASPHALT WIDTH DIMENSIONS. THIS WAS PREVIOUSLY DISCUSSED AT THE PRE-CON INSPECTION WITH AMERSON SURVEY PRESENT. SURVEY AT BACK OF CURB MUST ALLOW FOR 1.5" CURB BATTER. |
|
11/04/2008 | GRADING - INTERMEDIATE | Continued | UNDERGROUND UTILITY CONSTRUCTION IN PROGRESS | |
10/27/2008 | GRADING - INTERMEDIATE | Continued | WATER AND SEWER LINES SHOULD BE COMPLETE IN ONE WEEK, DRY UTILITIES WILL START 10/29/08 AND SHOULD BE COMPLETE IN 2-3 WEEKS. | |
10/21/2008 | GRADING - INTERMEDIATE | Continued | UNDERGROUND UTILITY CONSTRUCTION IN PROGRESS | |
10/01/2008 | GRADING - INTERMEDIATE | Continued | UNDERGROUND R/D BASIN INSTALLED AND BACKFILLED. THE CATCH BASIN AND HATCHES NEED TO BE INSTALLED TO PREVENT UN-AUTHORIZED ENTRY. UNDERGROUND UTILITY CONSTRUCTION WILL BEGIN NEXT WEEK. I REITERATED TO QUAIN QUAIN THAT THE PAAL MEASUREMENT WOULD BE MEASURED ON THE PAVEMENT, AND THAT AMERSON SURVEY HAD BEEN INFORMED AT THE PRE-CON MEETING. |
|
10/01/2008 | GRADING - INTERMEDIATE | Continued | R/D BASIN INSTALLED, NEEDS CATCH BASIN AND HATCHES INSTALLED TO PREVENT UNAUTHORIZED ENTRY. CALL FOR INSPECTION WHEN UNDERGROUND UTILITIES ARE COMPLETE. PAAL MEASURED ON PAVEMENT. |