Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
Permit Number - T07BU02618
Inspection Description - STORMWATER INSTALL OF CONTROLS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2008 | STORMWATER INSTALL OF CONTROLS | Approved | ||
07/08/2008 | STORMWATER INSTALL OF CONTROLS | Correction Required | 1. CLOSE OFF ALL CURB ACCESS ON LEE EXCEPT FOR THE STABILIZED CONSTRUCTION ENTRANCE (SCE). 2. ALL CONSTRUCTION ACCESS MUST BE THROUGH THE SCE. 3. LEE STREET MUST BE KEPT CLEAN AT ALL TIMES. SWEEPING MUST OCCUR AS NEEDED THROUGHOUT THE DAY. 4. SWEEP LEE STREET OF ALL SOIL AND SEDIMENT BEFORE THE AFTERNOON RAIN EVENT. |
|
06/30/2008 | STORMWATER INSTALL OF CONTROLS | Correction Required | NO WATTLE ON N&W PERIMETERS CALLED CHIN CHIN AT 10:40 AM TOLD HIM WATTLE MUST BE INSTALLED BY 3:00PM 4:10 PM INSPECTION, NO WATTLE ON N&W BY 10:00 AM ON JULY 1, 2008. ALSO NEED ROCK ENTRANCE. OR STOP WORK ORDER WILL BE ISSUED. |
|
06/26/2008 | STORMWATER INSTALL OF CONTROLS | Correction Required | STORMWATER CONTROLS NEED TO BE PLACED ON NORTH AND WEST PERIMETERS. GRUBBING IS IN PROGRESS. |