Permit: T07BU02618


Addresses:

1631 N SWAN RD

Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Date Description Inspector Results Comments
06/16/2009 ENGINEERING PRE-CONSTRUCTION Approved
07/09/2008 ENGINEERING PRE-CONSTRUCTION Correction Required NEED A CURRENT AZPDES CONST. GP AND SWPPP UPDATES.
06/26/2008 ENGINEERING PRE-CONSTRUCTION Partial Approval ON SITE MEETING WITH QAIN QAIN, MIKE AMERSON (SURVEYOR) , AND MATT HAZEN AND DAVE MADDEN OF EAGLE ROCK EXCAVATING

1. DEVELOPER MUST PROVIDE A CURRENT AZPDES CONSTRUCTION GP.
2. FINISHED 24' PAAL WIDTHS AND PARKING SHALL BE MEASURED AT ASPHALT LEVEL.
3. COMPLETED PRE-CON FORM RECEIVED.
06/09/2008 ENGINEERING PRE-CONSTRUCTION Partial Approval PARTIAL PRE-CON,
I REVIEWED SWPPP AND GRADING PLAN WITH QIAN QIAN SHAO 909-3381/VENTURE WEST.
1. POST AZPDES AUTHORIZATION, PERMIT AND PLANS ON-SITE.
2. OK TO USE STRAW WATTEL TO DETAIL PROVIDED. MUST CALL FOR INSTALL OF CONTROLS FOR DAY WHEN SITE GRUBBING OCCURS. PERIMETER GRUBBING AND SWPPP INSTALLATION SHALL OCCUR SIMULTANEOUSLY.
3. REVIEW PRE-CON DOCUMENT AND PROVIDE A COPY OF THE DOCUMENT TO THE INSPECTOR AT THE NEXT INSPECTION.