Permit: T07BU02444

Parcel: 122184340


Addresses:

3501 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
08/19/2010 STORMWATER FOLLOW-UP INSP Approved
08/10/2010 STORMWATER FOLLOW-UP INSP Approved SITE IS APPROXIMATELY 90% STABILIZED, TEMP SEDIMENT CONTROLS HAVE BEEN REMOVED
07/16/2010 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/07/2010 STORMWATER FOLLOW-UP INSP Continued 1) ELIMINATED ONE ACCESS WAY FROM ROW TO BLDG. TO INCLUDE SIDEWALKS AND HC RAMPS (NEED REVISED PLAN).
2) CHANGE FROM VERTICAL CURB TO EXTRUDED CURB ALONG EAST AND NE SIDE PARKING AREA.
3) PROVIDE A REVISED PLAN SHOWING ALL CHANGES MADE FROM THE ORIGINAL APPROVED PLAN, PRIOR TO FINAL GRADING APPROVAL.
4) PROVIDE ENGINEERING CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT THE STORM DRAINAGE SYSTEM AND RET/DET BASINS WERE COMPLETED PER THE APPROVED GRADING PLAN.
5) ENSURE STORM WATER MAINT INSPECTIONS ARE PERFORMED AND DOCUMENTED.
6) REMOVE TEMP SEDIMENT CONTROLS IN AREAS WHERE CURBING IS IN PLACE.
05/25/2010 STORMWATER FOLLOW-UP INSP Continued 1) CAN REMOVE STORM WATER CONTROLS (SILT SOCK) ALONG SPEEDWAY.
2) HAVE QUESTIONS ABOUT ROOF DRAINAGE FROM ADJACENT PROPERTY ALONG EAST SIDE OF SITE.
3) ENSURE SPOILS FROM FOOTINGS OF PERIMETER WALLS REMAIN ON SITE.

CALL FOR ANY QUESTIONS OR CONCERNS.
( MIKE JOHNSON - CHESNUT 733-3300)
04/07/2010 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
NO SITE WORK AT THIS TIME, HOWEVER BASINS HAVE BEEN ROUGHED IN AND AN OUTLET STRUCTURE HAS BEEN COMPLETED. NO OTHER SITE WIRK IS BEING DONE.
03/10/2010 STORMWATER FOLLOW-UP INSP Continued NO STORM WATER CONCERNS
03/02/2010 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. SWEEP UP TRACKING OFF OF SURROUNDING ROADWAYS.
NO CHANGES TO SITE WORK.
01/28/2010 STORMWATER FOLLOW-UP INSP Continued CONTRACTORS ERECTING STEEL BLDG, NO SITE WORK COMPLETED EXCEPT FOR A SMALL BASIN ROUGHED IN.
NO STORM WATER CONCERNS AT THIS TIME
01/12/2010 STORMWATER FOLLOW-UP INSP Continued NO CHANGES AND/OR CONCERNS ON SITE. NO STORM WATER ISSUES AT THIS TIME
12/23/2009 STORMWATER FOLLOW-UP INSP Continued STORM WATER ITEMS LISTED UNDER THE PREVIOUS INSPECTION HAVE BEEN ADDRESSED - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/08/2009 STORMWATER FOLLOW-UP INSP Correction Required 1) RE-ESTABLISH YOUR STABILIZED CONSTRUCTION ENTRANCE REQUIRED BY YOUR SWPPP.
2) LOWER, BENCH AND/OR REMOVE STOCKPILED MATERIAL ALONG SOUTH WEST CORNER OF SITE. SUPPLEMENTAL SEDIMENT CONTROLS CAN BE PLACED AROUND STOCKPILE TO TRY AND KEEP MATERIAL FROM LEAVING THE SITE.
11/18/2009 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR ON SITE, WORK HAS STARTED UP AGAIN.
TEMP SEDIMENT CONTROLS IN PLACE, NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
11/04/2009 STORMWATER FOLLOW-UP INSP Not ready for Inspection NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME, NO ACTIVITY ON SITE
08/12/2009 STORMWATER FOLLOW-UP INSP Continued SEDIMENT CONTROLS ARE IN PLACE AND HAVE BEEN MAINTAINED. NO STORM WATRER CONCERNS AT THIS TIME
07/21/2009 STORMWATER FOLLOW-UP INSP Continued STORM WATER SEDIMENT CONTROLS ARE IN PLACE. SITE IS IN COMPLIANCE WITH THERE SWPPP.
NO CONSTRUCTION ACTIVITY ON SITE. ROW ENTRANCES HAVE BEEN INSTALLED.
06/24/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
05/18/2009 STORMWATER FOLLOW-UP INSP Continued NO STORM WATER CONCERNS/ NO ACTIVITY ON SITE/ NO CONSTRUCTION BEING DONE??
04/28/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
04/21/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAYS ON A ROUTINE BASIS.