Inspection Status: Continued
Inspection History: GRADING - INTERMEDIATE
Permit Number - T07BU01991
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Continued
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2013 | GRADING - INTERMEDIATE | Continued | NEW RAMP ADDED SOUTH OF LOT 9 . | |
10/28/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON LOTS #5 AND #9 | |
08/05/2013 | GRADING - INTERMEDIATE | Continued | WALKED LOT #10 WITH BILLY. | |
08/01/2013 | GRADING - INTERMEDIATE | Continued | NO GRADING ACTIVITY . | |
06/17/2013 | GRADING - INTERMEDIATE | Continued | WALKED SITE WITH BILL AND DAVE SIDE WALKS OVER 2% AT LOT #10 .AND NEEDS TO ADD WASH OUT. | |
05/08/2013 | GRADING - INTERMEDIATE | Continued | GOT WITH GC NO GRADING ACTIVITY. | |
04/30/2013 | GRADING - INTERMEDIATE | Continued | STARTING TO WORK ON HOUSE PAD #9. | |
04/25/2013 | GRADING - INTERMEDIATE | Continued | NO GRADING ACTIVITY AT THIS TIME. | |
04/12/2013 | GRADING - INTERMEDIATE | Continued | NO GRADING ACTIVITY AT THIS TIME. | |
04/09/2013 | GRADING - INTERMEDIATE | Continued | NO GRADING ACTIVITY AT THIS TIME. WORKING ON HOUSES #5 AND #10. | |
04/01/2013 | GRADING - INTERMEDIATE | Continued | DTARTING TO GRAD AROUND LOT #10. | |
03/19/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON #5 HOUSE PAD GOT WITH GRADING CONTRACTOR TO REPAIR SWPPP CONTROLS . | |
02/27/2013 | GRADING - INTERMEDIATE | Continued | WASHOUT HAS BEEN INSTALLED ON SITE. | |
02/19/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON HOUSE PADS . | |
02/07/2013 | GRADING - INTERMEDIATE | Continued | GOT WITH CONTRACTOR TO POVIDE WASH OUT. | |
01/28/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON RIP- RAP ON NORTH SIDE OF SITE . SIDE WALK HAS BEEN ADDED TO LOT #3. THIS WILL NEED TO BE ADDED TO FINAL REVION. | |
01/04/2013 | GRADING - INTERMEDIATE | Continued | INSTALLING RIP-RAP ON NORTH SIDE OF SITE. | |
11/27/2012 | GRADING - INTERMEDIATE | Continued | CONTOLS ARE IN PLACE. | |
11/19/2012 | GRADING - INTERMEDIATE | Continued | MET WITH BILL ABOUT PROVIDING AP AS BUILTS FOR ALL CHANGES. | |
12/09/2011 | GRADING - INTERMEDIATE | Continued | MET WITH LAITH AND THE DEVELOPER AND DISCUSSED WHAT IS GOING TO HAPPEN IN THE NEAR FUTURE. CURRENTLY THEY ARE WORKING ON PURCHASING THE PROPERTY AND WILL THEN PLACE A SUBSTITUTE ASSURANCE AGAINST THE SITE. IN THE NEXT MONTH THEY WILL BE ASKING FOR LOT RELEASES FOR LOT 1-3, AND WILL BE WORKING ON REVISED DRAWINGS AND DSMR'S FOR THE SITE TO CHANGE SOME OF THE DRAINAGE ITEMS. HAVE ADVISED ALL IS CONTINGENT OF THE PLACEMENT OF THE THIRD PARTY LAND TRUST TO START THIS PROCESS OFF. I PULLED THE ORIGINALLY APPROVED PLANS AND THE REVISED DRAWINGS AND GAVE THEM TO LAITH FOR THE CONSIDERATION OF WHAT CAN BE CHANGED IN THE DRAINAGE ASPECTS. |