Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T07BU01927
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/25/2009 | GRADING - INTERMEDIATE | Approved | ||
04/17/2009 | GRADING - INTERMEDIATE | Prior to Final Inspectn | OK FOR TYPE 3 SIDEWALK SCUPPER IN R.O.W. INSTALLATION TO BE COORDINATED WITH PAT WHIDDON PERMITS/CODES. REVISIONS TO BE SHOWN ON THE FINAL APPROVED GRADING PLAN WITH AN ENGINEERS CERTIFICATION LETTER. |
|
03/24/2009 | GRADING - INTERMEDIATE | Continued | CURB FORMS AT SOUTH END OF PROPERTY OK FOR PAAL DIMENSIONS. | |
11/04/2008 | GRADING - INTERMEDIATE | Correction Required | PROVIDE WEEP HOLES IN EAST BANK OF DRAINAGE CHANNEL | |
05/29/2008 | GRADING - INTERMEDIATE | Partial Approval | ||
04/24/2008 | GRADING - INTERMEDIATE | Partial Approval | DRAINAGE CHANNEL AND SLOPES ARE BEING PREPPED FOR PLACEMENT OF CONCRETE SIDE AND BOTTOM. NOTES FROM PRE-CON SUPERINTENDENT: ERIC 1. PROVIDE A LETTER OF CERTIFICATION FROM THE ARIZONA REGISTERED P.E. THAT CERTIFIES THAT THE PROJECT AND THE DRAINAGE IMPROVEMENTS ARE CONSTRUCTED TO THE APPROVED GRADING PLANS. LETTER IS REQUIRED PRIOR TO C OF O APPROVAL. 2. PROVIDE AN ENGINEERED AND STAMPED DETAIL THAT SHOWS THE TIE-IN CONNECTION BETWEEN NEW CONCRETE AND EXISTING CONCRETE IN DRAINAGE CHANNEL. 3. MAINTAIN A CLEAR, CLEAN, COMPACTED CHANNEL BOTTOM AND COMPACTED SLOPES UNTIL THE CONCRETE CHANNEL IS COMPLETED. |