Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T07BU01882
Inspection Description - GRADING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2010 | GRADING - FINAL | Approved | All items complete, Approved | |
| 04/15/2010 | GRADING - FINAL | Denied | Need to complwete items1,7,11,12,15 & 20 from the 7/10 punch list, also need to provide basin cert from EOR, and remove all construction material and debris from site. | |
| 09/03/2009 | GRADING - FINAL | Denied | Met with contractor and owner to go over punch list items. Item 2,4,6,7 and 10 are complete. All remaining items need to be finished. Owner thought the rest of the items would be finished by the end of the month. | |
| 07/27/2009 | GRADING - FINAL | Denied | Met with GC and eng. of record to discuss punch list, few items will need to go to DSD for changes or revisions, they are working on may items on punch list and should have them complete in the next two weeks. Will hold bldg's 4&5 until all items resolved. | |
| 07/10/2009 | GRADING - FINAL | Denied | Preliminary punch list; 1) Address all roof down spouts that cross sidewalks per notes 12 and 21 of development plan. 2) Install 5 ft sidewalk in parking lot adjacent to Bldg 4 and 5 per Dev. PLan and grading plan. 3) Install water harvest areas in parking lot and around buildings per Dev.plan #17 and detail J sht. 2 4) Install fire acess gate per note #7 Dev. plan Sht. 2 5) Finish outside of east property line wall per note 18 Dev plan sht #2 6) All outdoor lighting shall have a max. height of 16 ft. 7) Install HC parking signs. 8) HC ramps north of entrance not installed per detail 9) Install storm basin at NW praking lot per detail E sht 4 Dev. Plan 10) Install wall opening per note 44 Sht 5 Dev. Plan 11) Install HC parking and sidewalk per Dev plan at Bldg 8. 12) Install all bike parking per approved plan. 13) Install one way signs and arrows at both entrances per plan. 14) Install screen wall south of entrance along Alvernon per plan. 15) Install sidewalk and stripping at entrance off of Alvernon. 16) Stripe loading zones in parking area off POe Street. 17) Install curbing and screen wall in parking area off Poe St. 18) Construct basin and railing along Holmes St. per detail L Sht 3. grading plan. 19) Install weep holes in retaining walls per note 3 Sht 6 grading plan. 20) Install all signage and stripping at entrances per grading plan. 21) revise Dev. Plan and grading plan to match what was constructed and re-submit for approval. 22) Intsall hand railing at sidewlk to parking lot, 2 places. Call for re-inspections |