Inspection Status: Closed
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 04/22/2020 |
GRADING - INTERMEDIATE |
|
Closed |
SITE WAS NOT CONSTRUCTED PER THESE APPROVED PLANS, SEE ADDRESSES FOR ADDITIONAL INFORMATION UNDER NEW DEVELOPMENT PACKAGES AND THEIR INSPECTIONS. |
| 03/22/2012 |
GRADING - INTERMEDIATE |
|
Continued |
NO CHANGES IN THE SITE AT THIS TIME. |
| 01/31/2012 |
GRADING - INTERMEDIATE |
|
Continued |
NO CHANGES IN THE SITE AT THIS TIME. |
| 11/08/2011 |
GRADING - INTERMEDIATE |
|
Continued |
NO WORK AT THIS TIME. |
| 09/19/2011 |
GRADING - INTERMEDIATE |
|
Continued |
CHECKED THE SITE TO SEE WHAT WORK HAS BEEN COMPLETED. WILL NEED TO MEET WITH THE ENGINEER OF RECORD AND THE CONTRACTORS TO SEE WHAT IT IS THAT THEY ARE WANTING TO DO SINCE THE SITE WILL BE PLACED ON HOLD. |
| 08/24/2011 |
GRADING - INTERMEDIATE |
|
Continued |
CREWS CONTINUE TO WORK AROUND THE SITE, BUT THERE IS NOTHING BEING COMPLETED AT THIS TIME. HAVE ADVISED THE CREW THAT i WILL BE AWAY FROM THIS SITE FOR THE NEXT 3 WEEKS AND SHOULD RETURN ON 9/19/2011. |
| 07/18/2011 |
GRADING - INTERMEDIATE |
|
Continued |
THE CREWS ARE WORKING ON THE FOLLOWING AREAS AT THIS TIME: FORMING AND POURING THE CURB RETURNS ON THE WEST SIDE OF THE CENTER ENTRANCE, THE EAST SIDE WAS POURED LAST WEEK WITH THE MEDIAN ISLANDS ON GOLF LINKS ROAD. FORMING THE EAST AND WEST CURB RETURNS ON THE EAST ENTRANCE, PREPARING IT FOR CONCRETE LATER ON TODAY. GRADING IN THE MEDIAN ISLAND AREA ON GOLF LINKS ROAD PREPARING THE AREA FOR THE AC PLACEMENT THAT WILL HAPPEN LATER ON THIS WEEK. ALL OF THE ABOVE MENTIONED WORK IS BEING WATCHED BY THE PIA INSPECTORS FROM THE TRANSPORTATION DEPARTMENT. |
| 06/01/2011 |
GRADING - INTERMEDIATE |
|
Continued |
THE STOCKPILE OF EXCESS MATERIAL THAT HAD BEEN LOCATED ON THE EAST SIDE OF THE SITE IS BEING REMOVED AND UTILIZED AS BACKFILL MATERIAL ALONG THE RETAINING WALL. IT HAS BEEN ADVISED THAT ALL THE WORK ON THIS SITE BE CHECKED BY THE ENGINEER OF RECORD SO THAT HE CAN WRITE HIS CERTIFICATION LETTER AT THE END OF THIS PROJECTS ACCEPTANCE. |
| 05/31/2011 |
GRADING - INTERMEDIATE |
|
Continued |
MET ON-SITE WITH THE FORMAN FROM MAGNUMN PAVING TO DISCUSS THE UPCOMING WORK ON THE STORMDRAIN INSTALLATION ON PRIVATE PROPERTTY FOR THE NEW QUIK-TRIP. THEY WILL BE POURING THE MANHOLE BASES LATER THIS WEEK AND WILL CALL FOR AN INSPECTION ON THE DAY THAT THEY POUR.. ONCE THIS WORK IS DONE THE CONTRACTOR FOR THE QUIK TRIP WILL BE MOBILIZING SO THAT THEY CAN BE GIN THWIR CONTRACT WORK ON THE NEW BUILDING. |
| 05/17/2011 |
GRADING - INTERMEDIATE |
|
Continued |
THE CREW IS WORKING ON THE INSTALLATION OF THE STORD DRAIN PIPES FROM GOLFLINKS THROUGH THE SITE OVER TO THE WAS THAT RUNS ALONG THE SOUTH SIDE OF THE SITE. REMINDED THE CONTRACTOR(MAGNUMN PAVING) THAT PORTIONS OF THIS WORK NEEDS TO BE INSPECTED BY THE RIGHT-O-WAY DEPARTMENTS SINCE IT IS WITHIN THE CITIES PROPERTY. THEY WILL CONTACT RICHARD LEIGH TO SCHEDULE THIS WORK IN THE FUTURE. THE CREWS ARE ALSO WORKING ON THE SEWERLINE INSTALLATION ALONG THE SOUTH SIDE OF THE SITE NORTH OF THE RETAINING WALL. A CREW IS ALSO WORKING ON CONTINUEING THE RETAINING WALL INSTALLATION, THE TOP HALF OF THE EASTERN END. |