Permit: T07BU01842

Inspection Status: Closed

Inspection History: GRADING - CHECK FOR ACTIVITY

Date Description Inspector Results Comments
04/22/2020 GRADING - CHECK FOR ACTIVITY Closed SITE WAS NOT CONSTRUCTED PER THESE APPROVED PLANS, SEE ADDRESSES FOR ADDITIONAL INFORMATION UNDER NEW DEVELOPMENT PACKAGES AND THEIR INSPECTIONS.
01/31/2012 GRADING - CHECK FOR ACTIVITY Continued NO CHANGES IN THE SITE AT THIS TIME.
07/18/2011 GRADING - CHECK FOR ACTIVITY Continued THE CREWS ARE WORKING ON THE FOLLOWING AREAS AT THIS TIME: FORMING AND POURING THE CURB RETURNS ON THE WEST SIDE OF THE CENTER ENTRANCE, THE EAST SIDE WAS POURED LAST WEEK WITH THE MEDIAN ISLANDS ON GOLF LINKS ROAD. FORMING THE EAST AND WEST CURB RETURNS ON THE EAST ENTRANCE, PREPARING IT FOR CONCRETE LATER ON TODAY. GRADING IN THE MEDIAN ISLAND AREA ON GOLF LINKS ROAD PREPARING THE AREA FOR THE AC PLACEMENT THAT WILL HAPPEN LATER ON THIS WEEK. ALL OF THE ABOVE MENTIONED WORK IS BEING WATCHED BY THE PIA INSPECTORS FROM THE TRANSPORTATION DEPARTMENT.
06/01/2011 GRADING - CHECK FOR ACTIVITY Continued CREWS CONTINUE TO WORK ON THE INSTALLATION OF BACKFILL ALONG THE NORTHSIDE OF THE RETAINING WALL AS THE MANHOLE FORMS ARE BEING REMOVED. THIS WORK SHOULD CONTINUE THROUGH THE END OF THE WEEK.
04/08/2011 GRADING - CHECK FOR ACTIVITY Continued WORKING ON MOVING AND WATERING MATERIAL ON SITE, AND CONTINUING WITH THE INSTALLATION OF REBAR FOR THE RETAINING WALL ALONG THE SOUTH SIDE OF THE QUIK TRIP LOCATION.
02/25/2011 GRADING - CHECK FOR ACTIVITY Continued GRADING OF THE SITE IS TAKING PLACE, RETAINING WALL FOOTER EXCAVATION WEST OF HOUGHTON, AN INSTALATION OF THE SEWER LINE FROM BONANZA TO THE SITE. THE PIPE SHOULD BE DONE BY THE END OF THE MONTH AND THE FILL WORK COMPLETED SOMETIME IN MARCH.
02/07/2011 GRADING - CHECK FOR ACTIVITY Continued CREWS CONTINUE TO WORK ON EXCAVATING THE EXCESS MATERIAL AND PLACINT IT INTO THE FILL LOCATIONS, THIS IS MONITORED BY THE ENGINEER OF RECORD. VERY LIMITED DUST AND TRACK OUT AT THIS TIME. ALSO INSTALLING THE SEWER LINE ON LURENE DR., HAVE LAID APPROXIMATELY 2 BLOCKS EAST OF BONANZA AVE.
01/20/2011 GRADING - CHECK FOR ACTIVITY Continued CREWS COMPLETED THE PLANT REMOVAL AND REMOVING OF ALL CACTUS INTO THE NURSERY. CONTINUEING THE FINAL WORK ON THE CACTUS GRUBBING. ALSO PLACING STORMWATER CONTROL ALONG THE SOUTH BOUNDARY.
01/19/2011 GRADING - CHECK FOR ACTIVITY Continued CREW WORKING ON THE CACTUS REMOVAL, PLACING MATERIAL INTO A NURSERY AT THE NORTHWEST SIDE OF THE SITE. THIS INCLUDES THE REMAINING BARREL AND THE SAGUARO, AND STARTED THE REMOVAL OF THE EXCESS PLANT MATERIAL.
10/19/2010 GRADING - CHECK FOR ACTIVITY Continued NO WORK AT THIS TIME.