Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2008 | BUILDING - PROGRESS | Approved | IVRS - Inspection :* | |
| 02/15/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* PARTIAL/EXTERIOR TEMP WALLS OK |
|
| 02/07/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* SOUTH SECTION OF TEMP NOTE: BATTINGS MUST BE VERTICAL AND HORIZONTAL |
|
| 02/02/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* FRAMING SOUTH END OF DEMO AFTER HRS. INSP. #150.00 CK#1023 |
|
| 02/01/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* G.L 6-5.5 DRY IN |
|
| 01/30/2008 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* NEED TO SEE NAILING ON TEMP WALLS |
|
| 01/29/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* BRACING OK ON SOUTH WALL |