Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T07BU01624

Parcel: 11811011C


Addresses:

949 W SILVERLAKE RD

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
09/26/2008 GRADING - FINAL Approved Letters OK per JIm F.
09/25/2008 GRADING - FINAL Partial Approval Contractor installed hydro-seed in basin.
09/23/2008 GRADING - FINAL Denied Per Jim F. OK to accept letters dated 9/10/08 for basin function. this addresses items 9 and 10, from punch list dated 8/20/08.
09/09/2008 GRADING - FINAL Denied Contractor needs to address items 4, 9, 10, and 12 from punch list dated 8-20-08.
08/28/2008 GRADING - FINAL Denied Met witrh Gus on site to look at curb work.
08/20/2008 GRADING - FINAL Denied Contractor needs to:
1- Install HC ramp infront parking area. (max 12 to 1)
2- Install headers on HC ramps.
3- Address PAALs, less then 24'. (23.5)
4- Address all basins holding water longer then 24 hours.
5- Backfill next to fence opening west side.
6- Address ponding in HC ramp west side of building.
7- Address all erosion east side of building.
8- Clean street east side of building.
9- Provide site cert. from engineer, per C.O.T drainage manaul chapter XIV (14), section 14.2 (7).
10- Provide letter from engineer, per C.O.T., D.S. 11-01.16.2, site built in conformance to spec.
11- Provide pos. flow into all basins.
12- Address stabilization in all basins. (side slopes)
13- Clean all wash out.
14- Address flap valve not closing.
15- Address note 6 on C-3. Vert. curb not installed.
16- Address sidewalk undermined.
17- Install tow down, per detail 8 on sheet C-1.
07/21/2008 GRADING - FINAL Correction Required Walked site with site super. Contractor needs to call in for inspection. Lots of erosion on site, rip rap not installed properly, basin holding water and flap valve not closing.
04/14/2008 GRADING - FINAL Partial Approval Spoke to Carl in regards to final inspection. Carl to call in when Best completes paving.
11/19/2007 GRADING - FINAL Partial Approval Contractor installed 18"HDPE pipe along eastside of building. Not installed per City of Tucson standard. Contractor will need to provide letter from engineer in regards to pipe installation and provide compaction test for backfill above the pipe zone.
Asbuilt elev. for southside is 76.00, northside 74.00.