Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2008 | GRADING - FINAL | Approved | APPROVED PER AS-BUILT PLAN | |
| 10/02/2008 | GRADING - FINAL | Partial Approval | PARTIAL PENDING APPROVED AS-BUILTS. | |
| 09/12/2008 | GRADING - FINAL | Denied | 1 PROVIDE AS-BUILT GRADING AND DEVELOPMENT PLANS TO THE C.O.T. FOR REVIEW AND APPROVAL. 2. PROVIDE A LETTER OF CERTIFICATION FROM THE ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT IS CONSTRUCTED TO THE APPROVED AS-BUILT GRADING AND DEVELOPMENT PLANS. THE LETTER MUST ALSO CERTIFY THE SITE DRAINAGE AND RETENTION/DETENTION BASIN. 3. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. 4. STABILIZE ALL AREAS WITH DISTURBED SOIL. 5. REPAIR ROCK RIP RAP ON EAST SLOPE OF R/D BASIN. 6. PROVIDE CLASS I BICYCLE PARKING PER "DETAIL N". 7. MODIFY DETAILS "M" AND "L" TO SHOW "AS-BUILT CONDITIONS" INCLUDING: 12' PORCHES, (3) CLASS ROOM ADDITION, AND BUILDING DIMENSIONS. 8. PROVIDE 24' PAAL ADJACENT TO THE TRASH ENCLOSURE. 9. STRIPE CROSSWALKS AND PAINT DIRECTIONAL ARROWS ON THE ASPHALT. 10. PROVIDE 20' PAAL AT EXIT DRIVEWAY (NEXT TO SAHAURO). 11. PROVIDE DEPRESSED CURB AT EDGE OF ASPHALT ON INGRESS/EGRESS EASMENT. 12. PROVIDE NO GREATER THAN 2% SLOPE IN ALL DIRECTON ON HANDICAP PARKING SPACES AND ACCESS AISLES. 13. PROVIDE HANDRAILS ON BOTH SIDES OF ALL RAMPS THAT EXCEED 6' IN LENGTH. (ANSI 405.8) 14. MATCH VERTICAL CURB AND EXTRUDED CURB ADJACENT TO NORTHEAST HANDICAP PARKING SPACE/RAMP TO CONTROL THE DRAINAGE AND EROSION AT THIS POINT. |