Permit: T07BU01593

Parcel: 11449027A

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
11/04/2008 STORMWATER FOLLOW-UP INSP Approved CONSTRUCTION COMPLETE
09/11/2008 STORMWATER FOLLOW-UP INSP Correction Required CLEAN UP AND REMOVE ALL CONCRETE RESIDUALS.
05/06/2008 STORMWATER FOLLOW-UP INSP Correction Required 1. REMOVE DIRT STOCK PILE FROM R/D BASIN
2. PROVIDE 30' X 50' X6" DEEP ROCK FOR STABILIZED CONSTRUCTION ENTRANCE.
3. SWEEP DIRT TRACK OUT FROM TANQUE VERDE ROAD.
4. HANDICAP PARKING SPACES AND ACCESS AISLES MUST HAE NO GREATER SLOPE THAT 2% IN ALL DIRECTIONS
04/24/2008 STORMWATER FOLLOW-UP INSP Correction Required 1. CLEAN UP CONCRETE SPILLS NOT IN DESIGNATED WASHOUT AREA.
2. CLOSE THE GAP BETWEEN THE R/D BERM AND THE RETAINING WALL AT SW CORNER OF BASIN.