Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2009 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 09/09/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | NO SITE WORK CHANGES FROM LAST INSPECTION. STORM WATER CONTROLS ARE IN NEED OF REPAIR AND/OR REPLACEMENT. SITE STILL UNDER STORM WATER PLAN UNTIL STABILIZED. NOTE: CHANGES FROM PLAN TO ACCESS, DRAINAGE DIRECTION, CATCH BASIN/FLOOR DRAIN - NO APPROVED PLAN SHOWING CHANGES MADE. |
|
| 08/20/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | NO ACTIVITY. SITE PERIMETER NEEDS SWEPT. SWPPP CONTROLS NEED RE-ESTABLISHED. | |
| 07/10/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | ENSURE CONTRACTOR PROVIDES AN APPROVED REVISED PLAN SHOWING CHANGES MADE ( FLOOR DRAIN, SOUTH SIDE OF SITE...). NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. RET/DET BASIN HOLDS WATER GREATER THAN 24 HOURS. | |
| 05/22/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. ENSURE YOU COMPLY WITH REQUIREMENTS UNDER YOUR SWPPP AND THE AZPDES PERMIT. |
|
| 03/07/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) CONTINUE TO UTILIZE CONCRETE WASH OUT AS NEEDED, AND DISPOSE OF WASTE WHEN FULL 2) REPAIR SILT FENCE ALONG NORTH SIDE OF SITE 3) RE-ESTABLISH STABILIZED CONSTRUCTION ENTRANCE 4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. 5) SWEEP UP ANY TRACKED SOIL BACK ONTO SITE AS NECESSARY. |