Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/17/2009 | ENGINEERING PRE-CONSTRUCTION | Approved | Contractor addressed SWPPP concerns. Provided paper work for pre-con. | |
| 03/11/2009 | ENGINEERING PRE-CONSTRUCTION | Denied | PRE-CON MEETING WITH GARY 370-6357 1. REVIEW AND FILL OUT THE PRE-CONSTRUCTION DOCUMENT. COPY THE COMPLETED FORM AND SUBMIT TO THE INSPECTOR. 2. PROVIDE POSITIVE DRAINAGE (PER THE GRADING PLAN) AT THE PERIMETER OF THE SITE AND INSTALL SEDIMENT AND EROSION CONSTROLS (BMP'S). 3. INSTALL SEDIMENT AND EROSION CONTROLS WHEREVER DRAINAGE CAN LEAVE THE SITE. 4. RE-INSTALL THE STABILIZED CONSTRUCTION ENTRANCE TO THE SWPPP DETAIL. 30' X 50' X 6"DEEP OF 3-6" FRACTURED ROCK. 5. UPDATE THE SWPPP TO SHOW ALL DRAINAGE AND BMP'S. |