| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/03/2008 | ENGINEERING PRE-CONSTRUCTION | Approved | MET WITH SUPERINTENDENT, DISCUSSED SWPPP. SEDIMENT CONTROLS HAVE BEN INSTALLED: SILT FENCE HAS BEEN PLACED ALONG THE WEST AND NORTH PERIMETER. A STABILIZED CONSTRUCTION ENTRANCE/EXIT HAS BEEN INSTALLED. STRAW BAILS HAVE BEEN PLACED AT THE INLET TO THE EXISTING RET/DET BASIN. A PORTION OF SILT FENCE ALONG THE NORTH END OF THE SITE WAS NOT INSTALLED PER THE SWPPP, DUE TO THE FACT THAT THE AREA WILL NOT BE DISTURBED. ENSURE THAT THE STORM WATER PLAN IS FOLLOWED. NOTIFY THE INSPECTOR OF ANY SIGNIFICANT CHANGES OR REVISIONS TO THE APPROVED GRADING PLAN. |
|
| 03/07/2008 | ENGINEERING PRE-CONSTRUCTION | Not ready for Inspection | NO ACTIVITY |