Permit: T07BU01380

Parcel: 141113860


Addresses:

9121 E CAMINO ABRIL

Inspection Status: Continued

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
12/14/2010 GRADING - FINAL Continued SITE IS 99% COMPLETE, BUT IS NOT PER THE APPROVED PLANS. THE DEVELOPER IS WORKING ON REVISING THE DRAWINGS TO REFLECT WHAT HAS BEEN CONSTRUCTED IN THE FIELD. A FINAL INSPECTION WILL NOT BE PERFORMED UNTIL THE REVISED DRAWINGS HAVE BEEN APPROVED BY BOTH THE ZONING AND ENGINEERING DEPARTMENTS.
06/23/2010 GRADING - FINAL Continued NO CONCERNS AT THIS TIME, MISSING SIDEWALK, DRIVEWAY, AND AC PAVEMENT AT THIS TIME. ROUGH CONSTRUCTION OF THE BUILDING IS COMPLETE.
01/20/2010 GRADING - FINAL Not ready for Inspection SITE CHECKED MAINLY FOR THE EXTENSION OF THE PERMIT TIME. SITE NOT READY AT THIS TIME FOR THE FINAL INSPECTION TO BE PERFORMED. THE TRASH ENCLOSURE IS NOT CONSTRUCTED PER OUR APPROVED STANDARDS AND WILL NEED APPROVAL FROM ENVIRONMENTAL SERVICES PRIOR TO FINAL ACCEPTANCE OF THE SITE. AS-BUILT DRAWINGS WILL BE REQUIRED FOR ALL OF THE MODIFICATIONS THAT HAVE BEEN MADE TO THIS SITE. ONE OF THE PARKING SPOTS HAVE BEEN REMOVED ADJACENT TO THE TRASH ENCLOSURE AND WILL NEED TO BE ACCEPTED BY ZONING AND ENGINEERING BEFORE THE C OF O INSPECTION CAN BE COMPLETED.