| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/13/2020 | STORMWATER FOLLOW-UP INSP | Approved | APPEARS TO BE CONSTRUCTED PER THE APPROVED PLANS WITHOUT THE FINAL INSPECTIONS BEING COMPLETED | |
| 12/15/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME. | |
| 09/27/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME. THE PLANS WILL NEED TO BE REVISED AND APPROVED PRIOR TO FINALING THIS PERMIT AND THE ISSUANCE OF THE FINAL C OF O. CHRIS THE SITE SUPERVISOR FOR THIS DEVELOPMENT WILL BE WORKING WITH THE OWNER GERALD BROWN AND THE ENGINEER OF RECORD TOM HOSACK TO MAKE ALL CORRECTIVE CHANGES TO THE APPROVED PLANS. | |
| 06/23/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME, MISSING SIDEWALK, DRIVEWAY, AND AC PAVEMENT AT THIS TIME. ROUGH CONSTRUCTION OF THE BUILDING IS COMPLETE. | |
| 06/14/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME, MODIFICATIONS WILL NEED TO BE MADE TO THE GRADING PLAN AND BE APPROVED PRIOR TO CALLING FOR THE FINAL GRADING INSPECTION. | |
| 09/21/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | Minor cleanup of sidewalk and roadway, check all other controls. | |
| 03/24/2009 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO CONCERNS CONTROLS IN PLACE AND BEING MAINTAINED |
|
| 02/19/2009 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO CONCERNS AT THIS TIME MAINTENANCE WORK IS BEING PERFORMED REGULARLY BY CHRIS |
|
| 01/28/2009 | STORMWATER FOLLOW-UP INSP | Partial Approval | CP-AZPDES INFORMATION TO BE POSTED FOR EACH LOT UNK-SWPPP LOG BOOK TO BE UPDATED PA-GENERAL HOUSEKEEPING TO BE ADDRESSED |
|
| 01/14/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | MET WITH CHRIS GUINTER 940-0563 CORRECTION REQUIRED 10 DAY FOLLOW UP ITEMS TO BE ADDRESSED: -AZPDES INFORMATION TO BE POSTED FOR EACH LOT -SWPPP LOG BOOK TO BE UPDATED -GENERAL HOUSEKEEPING TO BE ADDRESSED |
|
| 01/06/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | NO CHANGE IN SITE 2ND CORRECTION NOTICE SENT |
|
| 12/02/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | PERFORM MAINTENANCE ON SWPPP CONTROLS SWEEP UP TRACK OUT CONTAIN ALL CONSTRUCTION MATERIAL/DEBRIS |
|
| 07/24/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | CORRECTION NOTICE 5 DAYS -CONTAIN CONCRETE WASHOUT -CONTAIN ALL CONSTRUCTION DEBRIS -POST AZPDES AND SWPPP INFO -SWEEP ROADWAY |
|
| 05/30/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | SAND BAGS STILL NOT PLACED STREET STILL NEEDS TO BE SWEPT |
|
| 05/19/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | TRACK OUT ON STREET POSTINGS NOT COMPLETE OR IN PLACE WATTLE AT DROP INLET/SCUPPER NOT PER BMPS |
|
| 05/07/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | V-DITCH INSTALLED |