Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/24/2009 | GRADING - FINAL | Approved | Site stabilized with new park project. Project complete | |
| 12/23/2008 | GRADING - FINAL | Partial Approval | Spoke to Clint and told him that the site needs to be stabilized before we can release grading permit. He said he would talk to Barclay and let them know. Park project underway and will eventually stabilize site. | |
| 06/24/2008 | GRADING - FINAL | Partial Approval | All holes on west side OK for handrail installation. | |
| 05/20/2008 | GRADING - FINAL | Partial Approval | North 250 to 333, OK. South 50 to end, OK |
|
| 05/19/2008 | GRADING - FINAL | Partial Approval | Contractor using ramp as zero point between north and south. Inspected holes 1 thur 250 on north side. | |
| 05/13/2008 | GRADING - FINAL | Partial Approval | Met with Don and Jerry on site to look at safety barrier installation. Contractor needs to dig holes 6" wide and 21" deep. Holes need need to be cleaned out for inspection. | |
| 03/18/2008 | GRADING - FINAL | Continued | Ashton placing soil cement along NW portion of Santa Cruz. It apears that they are very close to final grade on both the east and west banks of project. | |
| 03/12/2008 | GRADING - FINAL | Continued | Met onsite with Kevin from CMX Eng. Randy Jones and Clint from Boarderland. CMX wanted to review operation of placing the soil cement. Witnessed placing soil cement on the west side of channel, CMX spoke to western test regarding their test proceedures and depth of lift measurments. Clint estimated that Ashton has approx. 8 daye left to finish. I mentioned to CMX that we will need an engineer cert. when project is finished. | |
| 02/21/2008 | GRADING - FINAL | Partial Approval | Contractor made repairs to erosion along Santa Cruz Wash. Erosion was noted on 2/20/08 by Jim Femling. Jim contacted Clint site super. | |
| 02/14/2008 | GRADING - FINAL | Continued | Contractor continues to install soil cement. Contractor needs to address track out. | |
| 02/13/2008 | GRADING - FINAL | Continued | Ashton Const. began placing soil cement today, I watched the placement along the east side of channel. Western Testing was onsite to test compaction and mix design. Samples were taken for break test. | |
| 01/30/2008 | GRADING - FINAL | Continued | Met with Borderland Const, CMX Engineering, and Construction Manager Randy Jones, to review and inspect the grading for the soil cement along the banks of the Santa Cruz. Borderland plans to use Ashland Const. to start placing the soil cement in approx. 2 weeks. They have begun to place the rip rap on the slopes Approx sta. 48+00 to 39+00. I explained that the Eng. of record CMX must inspect as soil cemet is placed, and approve mix design and compaction. CMX said that western Tech will handel testing and they will inspect periodically. Soil Cement will take about 2 months to place. |
|
| 01/03/2008 | GRADING - FINAL | Partial Approval | Received complaint call from homeowner in regards to 4 wheelers access wash. Contractor will install No Tres. Passing signs and re-install dirt berm at end of Drexel. | |
| 11/16/2007 | GRADING - FINAL | Not ready for Inspection | Spoke to Clint in regards to Santa Cruz work. Per e-mail from Matt F. contractor will need to have inspection completed by special inspector. Contractor will need to provide City of Tucson DSD copy of all inspections to close out permit. | |
| 11/13/2007 | GRADING - FINAL | Not ready for Inspection | Met Clint site super on site in regards to work in the Santa Cruz. I told Clint I did not think The City of Tucson was overseeing this project. Told Clint I will check with city engineer Matt F. |