Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T07BU01363

Parcel: 13709002B


Addresses:

1301 W IRVINGTON RD

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
11/24/2009 GRADING - FINAL Approved Site stabilized with new park project. Project complete
12/23/2008 GRADING - FINAL Partial Approval Spoke to Clint and told him that the site needs to be stabilized before we can release grading permit. He said he would talk to Barclay and let them know. Park project underway and will eventually stabilize site.
06/24/2008 GRADING - FINAL Partial Approval All holes on west side OK for handrail installation.
05/20/2008 GRADING - FINAL Partial Approval North 250 to 333, OK.
South 50 to end, OK
05/19/2008 GRADING - FINAL Partial Approval Contractor using ramp as zero point between north and south. Inspected holes 1 thur 250 on north side.
05/13/2008 GRADING - FINAL Partial Approval Met with Don and Jerry on site to look at safety barrier installation. Contractor needs to dig holes 6" wide and 21" deep. Holes need need to be cleaned out for inspection.
03/18/2008 GRADING - FINAL Continued Ashton placing soil cement along NW portion of Santa Cruz. It apears that they are very close to final grade on both the east and west banks of project.
03/12/2008 GRADING - FINAL Continued Met onsite with Kevin from CMX Eng. Randy Jones and Clint from Boarderland. CMX wanted to review operation of placing the soil cement. Witnessed placing soil cement on the west side of channel, CMX spoke to western test regarding their test proceedures and depth of lift measurments. Clint estimated that Ashton has approx. 8 daye left to finish. I mentioned to CMX that we will need an engineer cert. when project is finished.
02/21/2008 GRADING - FINAL Partial Approval Contractor made repairs to erosion along Santa Cruz Wash. Erosion was noted on 2/20/08 by Jim Femling. Jim contacted Clint site super.
02/14/2008 GRADING - FINAL Continued Contractor continues to install soil cement. Contractor needs to address track out.
02/13/2008 GRADING - FINAL Continued Ashton Const. began placing soil cement today, I watched the placement along the east side of channel. Western Testing was onsite to test compaction and mix design. Samples were taken for break test.
01/30/2008 GRADING - FINAL Continued Met with Borderland Const, CMX Engineering, and Construction Manager Randy Jones, to review and inspect the grading for the soil cement along the banks of the Santa Cruz. Borderland plans to use Ashland Const. to start placing the soil cement in approx. 2 weeks. They have begun to place the rip rap on the slopes Approx sta. 48+00 to 39+00. I explained that the Eng. of record CMX must inspect as soil cemet is placed, and approve mix design and compaction. CMX said that western Tech will handel testing and they will inspect periodically.
Soil Cement will take about 2 months to place.
01/03/2008 GRADING - FINAL Partial Approval Received complaint call from homeowner in regards to 4 wheelers access wash. Contractor will install No Tres. Passing signs and re-install dirt berm at end of Drexel.
11/16/2007 GRADING - FINAL Not ready for Inspection Spoke to Clint in regards to Santa Cruz work. Per e-mail from Matt F. contractor will need to have inspection completed by special inspector. Contractor will need to provide City of Tucson DSD copy of all inspections to close out permit.
11/13/2007 GRADING - FINAL Not ready for Inspection Met Clint site super on site in regards to work in the Santa Cruz. I told Clint I did not think The City of Tucson was overseeing this project. Told Clint I will check with city engineer Matt F.