Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T07BU01190
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/22/2020 | GRADING - INTERMEDIATE | Approved | SITE APPEARS TO BE COMPLETE AT THIS TIME | |
12/09/2011 | GRADING - INTERMEDIATE | Continued | ALL WORK ON THE WESTERN HALF APPEARS TO BE DONE AT THIS TIME. THERE ARE SOME MINOR ITEMS THAT WILL NEED TO BE ADDRESSED IN THE NEAR FUTURE, MINOR EROSION IS BEING NOTED AROUND THE SITE, BUT NO CONCERNS AT THIS TIME. | |
10/14/2011 | GRADING - INTERMEDIATE | Continued | DROVE THROUGH THE SITE TODAY, NO ONE IS WORKING ON SITE AT THIS TIME. YOU CAN SEE SIGNS THAT THE LANDSCAPERS ARE STILL WORKING ON THE IRRIGATION INSTALLATION AND PLANT INSTALLATION. | |
09/19/2011 | GRADING - INTERMEDIATE | Continued | DROVE THROUGH THE SITE TO SEE WHAT IS HAPPENING DURING MY ABSENCE. THE SITE WORK HAS BEEN DONE FOR THE PHASE I PORTION OF THE SITE, CURRENTLY THE LANDSCAPERS IS ALL THAT i HAVE SEEN PERFORMING WORK AT THIS TIME. | |
06/13/2011 | GRADING - INTERMEDIATE | Continued | CREWS CONTINUE TO WORK ON THE COVERING OF THE UTILITY LINES AND THE FIRE PROTECTION LINES. PREPARING THE AREAS FOR FINISH PAD CONSTRUCTION AND THEN THE FINAL GRADING OF THE ROADWAY SUBGRADE. | |
04/08/2011 | GRADING - INTERMEDIATE | Continued | CREWS WORKING ON THE INSTALLATION OF THE SEWER LINES ON THE SOUTH CENTRAL SECTION OF THE SITES INTERNAL ROADWAYS. NO CHANGE ON THE CHANNEL ALONG THE WEST SIDE OF THE SITE ADJACENT TO VISTA MONTANA. | |
02/22/2011 | GRADING - INTERMEDIATE | Correction Required | CONTACTED THE ENGINEER OF RECORD LAST WEEK ABOUT THE MODIFICATIONS TO THE OUTER DRAINAGE CHANNELS THAT HAVE BEEN CUT INCORRECTLY. REVISIONS FOR THE CUTS APPEAR TO BE UNACCEPTABLE AS THEY ARE AND WILL BE SUBMITTED AS REVISIONS TO THE ENGINEERING REVIEWER/LAITH ALSHAMI FOR ACCEPTANCE, THIS HAS NOT TAKEN PLACE AT THIS TIME. | |
02/15/2011 | GRADING - INTERMEDIATE | Correction Required | STOPPED BY THE SITE TO SEE WHAT PROGRESS HAS BEEN MADE SINCE MY LAST VISIT. A CREW IS PLACING ROCK RIP RAP ALONG THE WEST SIDE OF THE PROJECT. IT APPEARS THAT THE WORK HAS NOT BEEN DONE PER THE APPROVED PLANS, THE SLOPES ARE TOO STEEP TO SUPPORT RICK RIP RAP ON FILTER FABRIC IN THE DRAINAGE SWALE. THE SLOPE VALUES OF THE SWALE ARE CURRENTLY AT 1.5:1 AND ARE CALLED OUT ON THE PLAN AS 3:1. I CONTACTED MIKE WITH BORDERLAND AT 730-9698 AND ADVISED HIM THAT IT IS NOT PER THE PLANS AND WILL EITHER NEED TO BE CORRECTED OR AN APPROVED PLAN CHANGE WILL HAVE TO BE SUBMITTED AND APPROVED PRIOR TO ALLOWING ADDITIONAL PLACEMENT TO TAKE PLACE. I ALSO CONTACTED THE ENGINEER OF RECORD DAVID LITTLE AT 520-881-7480 AND ADVISED HIM OF THE CURRENT CONDITION AND WHAT IS NEEDED FOR US TO ALLOW THE WORK TO CONTINUE. HE WILL CHECK WITH HIS CURRENT ENGINEER FOR THE PROJECT TO SEE WHAT HE HAS CHANGED AND WHAT REASONING IS BEHIND HIS DECISION. |