Inspection History Details
Inspection Status: Closed
Inspection History: GRADING - FINAL
Permit Number - T07BU01161
Inspection Description - GRADING - FINAL
Inspection Status - Closed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/05/2020 | GRADING - FINAL | Closed | SITE HAS NOT BEEN CONSTRUCTED PER THE APPROVED PLANS AND THIS PERMIT INSPECTION IS CLOSED AT THIS TIME. PLANS HAVE BEEN DESTROYED | |
05/05/2017 | GRADING - FINAL | Not ready for Inspection | NO MESSAGE NO ONE ON SITE. | |
06/07/2011 | GRADING - FINAL | Continued | NO ACTIVITY AT THIS TIME. | |
05/06/2011 | GRADING - FINAL | Continued | NO ACTIVITY. | |
03/24/2011 | GRADING - FINAL | Continued | NO ACTIVITY. | |
03/08/2010 | GRADING - FINAL | Continued | CONSTRUCTION FENCING HAS BLOWN DOWN CAUSING A HAZZARD IN RIGHT-OF-WAY. FENCING NEEDS TO BE FIXED. | |
01/20/2010 | GRADING - FINAL | Continued | MET WITH JIM FEMLING AND DAVID ROBERTS TO DISCUSS STATUS OF PROJECT. IT WAS DECIDED THAT CONTRACTOR NEEDS TO PROVIDE AS-BUILTS FOR THE PROJECT AND REQUEST A FINAL INSPECTION TO DETERMINE THE STATUS OF THE PROJECT. LEFT MESSAGE WITH DAVID FROM EAGLE ROCK EXPLAINING THE PROCESS. | |
01/07/2009 | GRADING - FINAL | Correction Required | Contractor needs to keep wattle in working order and pick up trash from around site. Spoke to Jose new site super. | |
03/28/2008 | GRADING - FINAL | Not ready for Inspection | Contractor provided letter from surveyor with basis of elevation. | |
03/25/2008 | GRADING - FINAL | Not ready for Inspection | Met with Randy onsite went over grading plan and survey stake out. Randy provided cut sheets for inspection. Went over stake out for buildings 4, 5 and 6. Contractor will need to provide letter from surveyor with basis of elevation. Contractor will need to provide approved grading plan for site. Contractor using set of drawings that are not approved. | |
03/21/2008 | GRADING - FINAL | Not ready for Inspection | Compared approved plans with survey stake out. Contractor needs to address problem found. |