Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/24/2007 | FIRE SPKLR - OH PIPING & HYDRO | Approved | ||
| 10/15/2007 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Site OK | |
| 08/30/2007 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Pressure test in attic, 1st floor, and 2nd floor OK Need plan and permit for interstitial layer of sprinkler heads added between the attic and third floor. |
|
| 08/22/2007 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Gate House only | |
| 08/14/2007 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Visual inspection - Ok to cover |