Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T07BU00794
Inspection Description - GRADING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2008 | GRADING - FINAL | Approved | Contractor to provide drainage letter with permit T07BU02468. | |
07/10/2008 | GRADING - FINAL | Denied | Met with super on site. Contractor needs to: (prelim punch list) 1- Provide approved revised drawing for inspection showing all changes. 2- Provide site cert. per C.O.T. drainage manaul chapter XIV, section 14.2 (7). 3- Address down spouts draining onto HC ramp. 4- Install wheel stops every where there is parking at a 5' sidewalk. 5- Address curb line rear of building (phase III) less then 6" reveal. Spoke to site super in regards to. |
|
04/21/2008 | GRADING - FINAL | Partial Approval | Met with Mario on site to look at grading in the rear of phase III. Contractor will need to provide a approved revised drawing showing all changes to the rear of the building. | |
04/01/2008 | GRADING - FINAL | Partial Approval | Contractor installed drainage for west loading dock. Inlet elev. , Discharge elev. , 49' of 6" pipe. | |
03/21/2008 | GRADING - FINAL | Partial Approval | Contractor install drainage pipe for east loading dock. Inlet inv. 10.07 and discharge inv. 7.94, installed per approved plan. | |
02/22/2008 | GRADING - FINAL | Denied | Contractor needs to: 1- Remove generator from ped. access path. 2- Remove port-a-potty. 3- Clean all wash out around site. 4- Separate all construction activity and debris from public access. 5- Stabilize all areas disturbed by construction. 6- Grade around box southwest corner to smooth uniform finish. 7- Stabilize all areas disturbed behind 1698, 1694, 1690 and 1686 W. Valencia Rd. 8- Install collars around clean outs. 9- Remove all trip hazards from ped. access path. 10- Remove mini storage unit or obtain permit. 11- Stripe bollards in trash enclosure. 12- Clean side slope next to drainage channel. 13- Provide 36" of clear area around all bike parking and 28" between racks. 14- Provide 5' sidewalk northeast corner of building. Spoke to Mario in regards to. |
|
12/17/2007 | GRADING - FINAL | Partial Approval | Met with Mario on site, went over minor changes to HC ramp building 2 and sidewalk building 1. I told Mario he will need to talk to LeeRay building inspector in regards to finals. |