Permit: T07BU00794


Addresses:

1702 W VALENCIA RD


Inspection Status: Approved

Inspection History: GRADING - FINAL

Permit Number - T07BU00794

Inspection Description - GRADING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
07/18/2008 GRADING - FINAL Approved Contractor to provide drainage letter with permit T07BU02468.
07/10/2008 GRADING - FINAL Denied Met with super on site. Contractor needs to: (prelim punch list)
1- Provide approved revised drawing for inspection showing all changes.
2- Provide site cert. per C.O.T. drainage manaul chapter XIV, section 14.2 (7).
3- Address down spouts draining onto HC ramp.
4- Install wheel stops every where there is parking at a 5' sidewalk.
5- Address curb line rear of building (phase III) less then 6" reveal.
Spoke to site super in regards to.
04/21/2008 GRADING - FINAL Partial Approval Met with Mario on site to look at grading in the rear of phase III. Contractor will need to provide a approved revised drawing showing all changes to the rear of the building.
04/01/2008 GRADING - FINAL Partial Approval Contractor installed drainage for west loading dock. Inlet elev. , Discharge elev. , 49' of 6" pipe.
03/21/2008 GRADING - FINAL Partial Approval Contractor install drainage pipe for east loading dock. Inlet inv. 10.07 and discharge inv. 7.94, installed per approved plan.
02/22/2008 GRADING - FINAL Denied Contractor needs to:
1- Remove generator from ped. access path.
2- Remove port-a-potty.
3- Clean all wash out around site.
4- Separate all construction activity and debris from public access.
5- Stabilize all areas disturbed by construction.
6- Grade around box southwest corner to smooth uniform finish.
7- Stabilize all areas disturbed behind 1698, 1694, 1690 and 1686 W. Valencia Rd.
8- Install collars around clean outs.
9- Remove all trip hazards from ped. access path.
10- Remove mini storage unit or obtain permit.
11- Stripe bollards in trash enclosure.
12- Clean side slope next to drainage channel.
13- Provide 36" of clear area around all bike parking and 28" between racks.
14- Provide 5' sidewalk northeast corner of building.
Spoke to Mario in regards to.