Permit: T07BU00794


Addresses:

1702 W VALENCIA RD


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T07BU00794

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
07/18/2008 STORMWATER FOLLOW-UP INSP Approved All areas stabilized.
04/18/2008 STORMWATER FOLLOW-UP INSP Partial Approval Contractor addressed otems from correction notice. Need to Mario on site and look at grading rear of building.
04/15/2008 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice. Contractor had 2 daqys to address:
1- Clean up wash out around site.
2- Install controls per SWPPP.
3- Cold patch all utility cuts.
4- Sweep south loading/parking area.
5- Wet area down for dust controls.
6- Install safety barrier around all equipment outside construction limits.
Spoke to Mario site super in regards to issues. If items are not addressed I will issue a stop work order.
04/01/2008 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to sweep rear of building behind fence. Track out.
12/27/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to:
1- Sweep northwest side of project.
2- Install controls around catch basin on northwest corner of project.
Spoke to site super in regards to.
12/10/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to keep travel lanes clean.
11/19/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice. Contractor needs to addrerss:
1- Replace wattle broken apart.
2- Clean up wash out around site.
3- Install wattle where needed.
4- Address discharge.
Spoke to site super in regards to. Contractor has 14 days to address items. If items are not addressed will issue a notice of violation.
10/05/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor addressed correction notice dated 10/3/07.
10/03/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued Correction Notice. Contractor has 2 days to:
1- Sweep parking area.
2- Replace wattle as needed.
3- Place sand bags on wattle.
4- Clean wash out around site.
5- Install a working wash out area.
If items are not addressed I will issue Notice of Violation. Gave contractor copy of new re-fee policy.
08/23/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Add controls to the northeast corner. Silt running off site.
2- Un-cover wattle on north side of project.
3- Install controls on west side per detail drawing.
Spoke to site super in regards to issues.
08/06/2007 STORMWATER FOLLOW-UP INSP Correction Required Silt running off north east side of project. Contractor needs to add controls to stop discharge.
08/02/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to add controls to the northeast side of the project.