Permit: T07BU00684

Parcel: 14042075A


Addresses:

2705 E EXECUTIVE DR

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
12/15/2009 GRADING - INTERMEDIATE Approved
11/24/2009 GRADING - INTERMEDIATE Continued Curb ramps at Executive Dr in, excavation for drainage swale from parking area at NW corner of lot not correct per plan, need to check with EOR.
11/18/2009 GRADING - INTERMEDIATE Partial Approval Checked curb ramps at Executive Dr. with contractor and approved to pour.
11/17/2009 GRADING - INTERMEDIATE Correction Required Check curb ramps with conc. contractor, 3 ramps need to be changed prior to pour, slopes do not meet 1:12 slope. We discussed options, all included some removeal of sidewalk and curbing.
10/22/2009 GRADING - INTERMEDIATE Partial Approval Contractor installing curb on site.
09/14/2009 GRADING - INTERMEDIATE Partial Approval 5ft sidewalk along Executive DR complete except for a small section, work continuing onsite.
08/06/2009 GRADING - INTERMEDIATE Continued Contractor beginning to pour conc. for parking lot.
07/31/2009 GRADING - INTERMEDIATE Continued LOOKED AT THE CURB THAT HAS BEEN POURED ON THE EAST ENTRANCE INTO THE SITE. THE CONTRACTOR HAS ASKED FOR THE APPROVAL OF THE CURB THAT HAS ALREADY BEEN POURED BY HIS SUB CONTRACTOR. THIS CURB APPEARS TO BE OF THE RIGHT HEIGHT AND APPEARS TO BE IN THE PROPER LOCATION, BUT THIS DETERMINATION WILL NEED TO BE VERIFIED BY EITHER THE SURVEYOR WHO LAID OUT THE ALLIGNMENT OR FROM THE ENGINEER OF RECORD FOR THIS SITE. THE CONTRACTOR HAS ASKED ABOUT THE SIDEWALK ALONG THE ADJACENT STREETS IF IT NEEDED TO BE REMOVED SINCE IT WAS IN GOOD SHAPE. i ADVISED HIM THAT HE WOULD NEED TO POSE THIS QUESTION TO THE ZONING AND ENGINEERING REVIEWERS WHO REVIEWED THE PLANS FOR COMPLIANCE. THEY HAVE SHOWN ON THE APPROVED GRADING PLANS THAT THE SIDEWALK IS TO BE REMOVED AND REPLACED WITH 5 FOOT NEW SIDEWALKS.
07/22/2009 GRADING - INTERMEDIATE Continued Contractor continuing to grade parking lot and install vertical curb.
07/20/2009 GRADING - INTERMEDIATE Partial Approval Contractor grading for parking lot will call for inspection on Wed., asked about sidewlk along Executive Way, I told him the plans call for 5ft wide walk and can tapper at property line onto adjacent property.
07/14/2009 GRADING - INTERMEDIATE Partial Approval curb and sidewalk in progress.