Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T07BU00436

Parcel: 13608477H

Inspection Status: Partial Approval

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
08/27/2008 GRADING - INTERMEDIATE Partial Approval ASPHALT AND STRIPING COMPLETE
VISUAL INSPECTION ONLY
08/20/2008 GRADING - INTERMEDIATE Partial Approval MET WITH RON ON SITE

DISCUSSED H/C PARKING-CLOSE TO 2% AT SUBGRADE
CAUTIONED PAVING CONTRACTOR H/C PARKING SPACES MUST BE MAX OF 2% AND ACCESSIBLE ROUTE MAX 5%
08/19/2008 GRADING - INTERMEDIATE Partial Approval SUB GRADE BEING PREPPED FOR PAVING
07/30/2008 GRADING - INTERMEDIATE Partial Approval VERIFIED ON SITE SIDWALK W/I 5% FOR ACCESSIBLE ROUTE

LOOKED AT OTHER SITE WORK
PAVING NOT YET STARTED
07/11/2008 GRADING - INTERMEDIATE Partial Approval NO NEW SITE WORK
06/26/2008 GRADING - INTERMEDIATE Partial Approval VERTICAL WORK CONTINUING
SITE WORK CONTINUING

MET WITH RON THOMAS AND OWNER ON SITE.

SLOPES ARE NOT THE SAME AS PLAN-RIP RAP IS NOT NECESSARY DUE TO FLATTER SLOPE-DG IS ACCEPTABLE PER LUC FOR STABILIZATION AS LONG AS SPLASH PADS/BLOCKS ARE PLACED AT ROOF DRAINS TO PREVENT EROSION.

DISCUSSED TRASH ENCLOSURE DOORS-THEY MUST PREVENT DEBRIS AND REFUSE FROM LEAVING ENCLOSURE AREA

BIKE RACK LOCATION CAN CHANGE SOMEWHAT IN ORDER TO BETTER ALLOW FOOT TRAFFIC
04/16/2008 GRADING - INTERMEDIATE Partial Approval PADS POURED
RETAINING WALL AT EAST SIDE CP
SITE WORK STILL BEING DONE
04/04/2008 GRADING - INTERMEDIATE Partial Approval CONCRETE TRUCKS ON SITE POURING PADS
04/03/2008 GRADING - INTERMEDIATE Partial Approval PAD FORM BOARDS UP
03/25/2008 GRADING - INTERMEDIATE Partial Approval SITE ROUGH GRADED
PAD WORK APPEARS TO BE STARTED
03/21/2008 GRADING - INTERMEDIATE Partial Approval SCE INSTALLED
03/20/2008 GRADING - INTERMEDIATE Partial Approval UTILITY TRENCHES ARE BACKFILLED
07/11/2007 GRADING - INTERMEDIATE Partial Approval MET WITH PAUL FOR CLARIFICATION ON PLANS