Permit: T07BU00352
Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/25/2008 | STORMWATER INSTALL OF CONTROLS | Approved | GRADER DITCH HAS BEEN COMPLETED AT NORTH AND EAST PERIMETERS. BOB MALLORY WILL INSPECT AND DETERMINE WHAT CONTROLS WILL BE INSTALLED FOR LOOSE GROUND ON SLOPES WHERE GRUBBING OCCURRED BEYOND THE GRADER DITCH. | |
| 04/24/2008 | STORMWATER INSTALL OF CONTROLS | Correction Required | GRADER DITCH AT PERIMETER IS REVERSED, CUT MUST BE ON OUTSIDE PERIMETER WITH WHEEL ROLLED BERM ON INSIDE. BO WILL REVERSE DITCH/BERM. |
|
| 04/23/2008 | STORMWATER INSTALL OF CONTROLS | Correction Required | 1. THE SECOND DAY OF GRUBBING IS IN PROGRESS, THE PERIMETER CONTROLS HAVE NOT BEEN INSTALLED. DAVE OLLANICK WILL CALL O'LEARY. THE CONTROLS MUST BE INSTALLED BY TOMORROW 4/24/08 OR STOP WORK WILL BE ISSUED. 2. RE-INSTALL STRING LINE AT SOUTH GRADING LIMIT. 3. POST THE AZPDES |
|
| 04/21/2008 | STORMWATER INSTALL OF CONTROLS | Partial Approval | STABILIZED CONSTRUCTION ENTRANCE IS IN PLACE. GRUBBING AND V-DITCH TO BE STARTED TOMORROW, CLEAR DRY WEATHER IS PREDICTED AND ALL CONTROLS WILL BE IMPLEMENTED THIS WEEK. |