Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
Permit Number - T07BU00352
Inspection Description - ENGINEERING PRE-CONSTRUCTION
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/21/2008 | ENGINEERING PRE-CONSTRUCTION | Approved | PRE-CON FORM WAS EMAILED TODAY. REVIEWED DOCUMENT WITH BOB MALLORY AND DAVE OLLANICK. | |
04/09/2008 | ENGINEERING PRE-CONSTRUCTION | Partial Approval | PRE-CON MEETING WITH OASIS TUCSON DAVID OLLANIK 322-3900 O'LEARY CONSTRUCTION V.P. PAUL McGILL 349-3303 GRADING & PAVING BO STANDIFER 349-6889 UNDERGROUND SUPRINTENDENT RANDY HERBERT 349-1709 1. STORMWATER CONTROLS WILL BE INSTALLED AS NORTH AND EAST PERIMETERS ARE BEING GRUBBED BEGINNING APRIL 21, 2008 AND COMPLETED ON 4/22/08. 2. FOLLOW-UP PRE-CON AND INSTALL OF CONTROLS INSPECTIONS WILL BE CALLED IN BY CONTRACTOR. 3. READ AND FILL IN THE BLANKS ON THE PRE-CON AND SWPPP DOCUMENTS AND PROVIDE A COPY OF THE COMPLETED PRE-CON DOCUMENT TO THE INSPECTOR AT THE NEXT INSPECTION. 4. POST THE AZPDES AUTHORIZATION AND UPDATE THE INFORMATION TO ADEQ. 5. PROVIDE A SCHEDULE FOR THE NORTH & EAST WALL CONSTRUCTION. |