Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/06/2009 |
GRADING - FINAL |
|
Approved |
Approved |
| 09/02/2008 |
GRADING - FINAL |
|
Denied |
All site work approvals conditional based on work being completed per approved asbuilt plan. Asbuilt plan has not been provided as of yet. |
| 08/15/2008 |
GRADING - FINAL |
|
Denied |
Met on site with Clint and Rick to go over punch list. Copy of punch list faxed to both on 8/20/08. |
| 08/15/2008 |
GRADING - FINAL |
|
Denied |
Contractor needs to complete punch list. |
| 06/27/2008 |
GRADING - FINAL |
|
Denied |
Will provide copy of punch list on Monday 6/30/08. Spoke to Clint in regards to Clint said it was OK. |
| 06/24/2008 |
GRADING - FINAL |
|
Partial Approval |
Met on site with Mike G. and J.C. Penny. Went over downspouts on southwest side of building. All water from down spouts need to be scuppered under sidewalk. Trash enclosure must be built per approved detail. Note 5 on sheet C1.29. Provided contractor copy of detail. |
| 06/02/2008 |
GRADING - FINAL |
|
Partial Approval |
Met with Clint on site, gave clint a copy of the prelin. punch list for Harkins. |
| 05/15/2008 |
GRADING - FINAL |
|
Not ready for Inspection |
Compiling punch list. |
| 04/22/2008 |
GRADING - FINAL |
|
Correction Required |
Met with Jim F. on site. Walked site, still large amount of work that needs to be completed before temp C of O. Items on punch list provided by contractor still not complete. |
| 04/08/2008 |
GRADING - FINAL |
|
Correction Required |
Met with Lisa, Mike G. LeeRay, Armondo, Jim F, Rick Lamotte, Loren and David R. Contractor will need to apply for a conditional C of O permit and provide a punch list of items to be complete before C of O can bee issued. |
| 04/07/2008 |
GRADING - FINAL |
|
Correction Required |
PAAL widths 23' 9" |
| 04/03/2008 |
GRADING - FINAL |
|
Not ready for Inspection |
Contractor not completing any work north of Best Buy. Contractor said Mike G. instructed them not to. |
| 03/27/2008 |
GRADING - FINAL |
|
Not ready for Inspection |
Met with Clint on site in regards to trash enclosure changes. I told Clint he needed to contact Andy Vera. |
| 03/14/2008 |
GRADING - FINAL |
|
Not ready for Inspection |
Met on site with the contractor building Best Buy. Contractor wanted a sidewalk inspection. I explained we do not do a sidewalk inspection. We just it is installed per D.S. or approved drawings. |
| 02/28/2008 |
GRADING - FINAL |
|
Continued |
Met with David R, Loren M and project manager to tour the site and check on progress for C of O in early May. Site is progressing well and appears that they will finish parking and frontage improvement by May. Does not appear that all bridges will be finished. |
| 02/11/2008 |
GRADING - FINAL |
|
Correction Required |
Summit builders called in for C of O for 5121 S. Calle Santa Cruz. No site work was completed. |
| 02/04/2008 |
GRADING - FINAL |
|
Correction Required |
Met on site with Mike site super, Loren and David with COT, in regards to a phased plan. I explained to all why we needed a phased plan. Mike said all site work will be completed before 1st. C of O is called in. |
| 01/29/2008 |
GRADING - FINAL |
|
Correction Required |
Spoke to Mike site super in regards to obtaining phased plan for C of O inspection. Also contractor will need to install truncated domes front of Best Buy. |
| 08/09/2007 |
GRADING - FINAL |
|
Partial Approval |
Contractor has new approved drawings showing PVC manholes. Permit number T06BU02533. |
| 07/10/2007 |
GRADING - FINAL |
|
Partial Approval |
Contractor installed stormpipe from sta. 1+75 to 3+90, per SD. |
| 04/03/2007 |
GRADING - FINAL |
|
Not ready for Inspection |
No activity at this time. |
| 02/01/2007 |
GRADING - FINAL |
|
Not ready for Inspection |
Contractor has been digging test holes around site. Contractor needs to schedule pre-con. |