Permit: T07BU00180

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
02/06/2009 GRADING - FINAL Approved Approved
09/02/2008 GRADING - FINAL Denied All site work approvals conditional based on work being completed per approved asbuilt plan. Asbuilt plan has not been provided as of yet.
08/15/2008 GRADING - FINAL Denied Met on site with Clint and Rick to go over punch list. Copy of punch list faxed to both on 8/20/08.
08/15/2008 GRADING - FINAL Denied Contractor needs to complete punch list.
06/27/2008 GRADING - FINAL Denied Will provide copy of punch list on Monday 6/30/08. Spoke to Clint in regards to Clint said it was OK.
06/24/2008 GRADING - FINAL Partial Approval Met on site with Mike G. and J.C. Penny. Went over downspouts on southwest side of building. All water from down spouts need to be scuppered under sidewalk. Trash enclosure must be built per approved detail. Note 5 on sheet C1.29. Provided contractor copy of detail.
06/02/2008 GRADING - FINAL Partial Approval Met with Clint on site, gave clint a copy of the prelin. punch list for Harkins.
05/15/2008 GRADING - FINAL Not ready for Inspection Compiling punch list.
04/22/2008 GRADING - FINAL Correction Required Met with Jim F. on site. Walked site, still large amount of work that needs to be completed before temp C of O. Items on punch list provided by contractor still not complete.
04/08/2008 GRADING - FINAL Correction Required Met with Lisa, Mike G. LeeRay, Armondo, Jim F, Rick Lamotte, Loren and David R. Contractor will need to apply for a conditional C of O permit and provide a punch list of items to be complete before C of O can bee issued.
04/07/2008 GRADING - FINAL Correction Required PAAL widths 23' 9"
04/03/2008 GRADING - FINAL Not ready for Inspection Contractor not completing any work north of Best Buy. Contractor said Mike G. instructed them not to.
03/27/2008 GRADING - FINAL Not ready for Inspection Met with Clint on site in regards to trash enclosure changes. I told Clint he needed to contact Andy Vera.
03/14/2008 GRADING - FINAL Not ready for Inspection Met on site with the contractor building Best Buy. Contractor wanted a sidewalk inspection. I explained we do not do a sidewalk inspection. We just it is installed per D.S. or approved drawings.
02/28/2008 GRADING - FINAL Continued Met with David R, Loren M and project manager to tour the site and check on progress for C of O in early May. Site is progressing well and appears that they will finish parking and frontage improvement by May. Does not appear that all bridges will be finished.
02/11/2008 GRADING - FINAL Correction Required Summit builders called in for C of O for 5121 S. Calle Santa Cruz. No site work was completed.
02/04/2008 GRADING - FINAL Correction Required Met on site with Mike site super, Loren and David with COT, in regards to a phased plan. I explained to all why we needed a phased plan. Mike said all site work will be completed before 1st. C of O is called in.
01/29/2008 GRADING - FINAL Correction Required Spoke to Mike site super in regards to obtaining phased plan for C of O inspection. Also contractor will need to install truncated domes front of Best Buy.
08/09/2007 GRADING - FINAL Partial Approval Contractor has new approved drawings showing PVC manholes. Permit number T06BU02533.
07/10/2007 GRADING - FINAL Partial Approval Contractor installed stormpipe from sta. 1+75 to 3+90, per SD.
04/03/2007 GRADING - FINAL Not ready for Inspection No activity at this time.
02/01/2007 GRADING - FINAL Not ready for Inspection Contractor has been digging test holes around site. Contractor needs to schedule pre-con.