Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 12/07/2007 |
GRADING - FINAL |
|
Approved |
Contractor completed all work, provided letter from engineer in regards to Slope bank. |
| 11/27/2007 |
GRADING - FINAL |
|
Not ready for Inspection |
Received letter from engineer in regards to chapter XIV, section 14.2 (7). |
| 11/06/2007 |
GRADING - FINAL |
|
Partial Approval |
No activity on site at this time. Spoke to Wally about calling in final inspection. |
| 10/15/2007 |
GRADING - FINAL |
|
Partial Approval |
Contractor needs to extend rip rap work. (1 to 1 slope) Spoke to Josh in regards to. |
| 08/13/2007 |
GRADING - FINAL |
|
Partial Approval |
Contractor installed hydro-seed in disturbed areas. |
| 07/02/2007 |
GRADING - FINAL |
|
Correction Required |
Contractor needs to stop washing streets down. Contractor washing mud down street. If contractor does not stop will issue notice of violation. Spoke to super on site. |
| 06/08/2007 |
GRADING - FINAL |
|
Partial Approval |
Contractor started construction. |