Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/27/2006 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 12/21/2006 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1. SHALL PROVIDE TEST ON ENTIRE GAS SYSTEM. 2. SHALL PROVIDE AGA OR CSA APPROVED GAS VALVES 3. SHALL PROVIDE RIDGID NIPPLE THRU FURNACE APPLIANCES HOUSING WITH SEDIMENT TRAP & SEDIMENT TRAP AT WATER HEATER. 4. VENT FROM FURNACE TO HAVE MINIMUM 1" CLEARANCE FROM COMBUSTIBLES FOR DOULBE WALL, 6" CLEARANCE IF SINGLE WALL. DOUBLE WALL THROUGH CEILING & ROOF TO POINT OF TERMINATION WITH APPROVED VENT CAPS. SHALL ALSO APPLY TO WATER HEATER. 5. PROVIDE BONDING OF BUILDING GAS PIPING TEST ON PIPING FROM NEW METER LOCATION TO STUB UP AT BUILDING SERVICE ENTRY (PARTIAL) SHALL TIE IN & RETEST ENTIRE SYSTEM. |