Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/13/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 11/09/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PROVIDE PSI TEST ON ALL GAS PIPING FOR UNITS #A & B |
|
| 11/02/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. ADD SUPPORT ON ROOF FOR GAS PIPING. 2. PROVIDE SEDIMENT TRAPS AT HEAT PACKS AND WATER HEATER. 3. UNIT B PROVIDE APPROVAL APPLIANCE CONNECTION FOR HEAT PACK. 4. PROVIDE ROOF JACK FOR PIPING THROUGH ROOF. |
|
| 10/31/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/30/2006 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* GAS PRESS. TEST -- METER TO NEW RUDD COMB. UNIT 1. COMB A/C FURN. WAS UNIT PERMITTED? 2. MISUSE/APPLICATION OF CSST FLEX MATERIAL ON GAS LINE. 3. ELECT. SWITCH AT ROOF! EXTERNALLY BRACE - UNSTABLE |
|
| 10/23/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. PROVIDE GAS PRESSURE TEST 2. PROVIDE LADDER TO GUT ON ROOF |