Inspection Status: Partial Approval
Inspection History: SITE - SEWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 4 PSI TEST ON PIPING OK |
|
| 01/30/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE SET, HCS LATERALS INSTALLED NEED VAC TEST NEED PIPING TEST |
|
| 01/26/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* ALL PIPING FROM PRIVATE MANHOLE LOCATION TO PUBLIC MANHOLE LOCATION INSTALLED WITH WYE FITTINGS FOR HCS CONNECTIONS. OK CAP OPEN HCS CONNECTIONS. WILL TEST AT LATER DATE HCS FROM PRIVATE MANHOLE TO LOT #5 D.I.P OK |
|
| 01/24/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* PRE-CON 11 AM SITE SEWER SHILOH W/STRUNK EXCAVATING 631-3944 WALTER - OWNER REP BOB - GREGOR ENGINEERING 8" PVC PLANS APPROVED PER 2003 UPC PRIVATE MANHOLE AND SEWER PIPING FROM PUBLIC MANHOLE TO HAVE CITY INSPECTIONS. TRACER WIRE AND BEDDING/SHADING REQUIRED ENGINEER WILL VERIFY GRADE AND REDLINE GRADE CHANGES |