Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/07/2006 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* 25 PSI TEST FROM METER PER PLAN OK |
|
| 08/30/2006 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 08/28/2006 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. PROVIDE OR HAVE ADDED TO PERMIT NEW WATER HEATER. 2. WATER HEATER TO BE IN WEATHERPROOF ENCLOSURE. 3. VENT FROM WATER HEATER TO HAVE 1" MINIMUM CLEARANCE FROM ROOF COMBUSTIBLE MATERIAL. 4. PROVIDE BONDING OF BUILDING GAS PIPING. 5. VENTS FROM FURNACE TO BE MADE UP CORRECTLY WITH 3 GALV SCREWS AT EACH JOINT. RETEST SYSTEM CALL IN FOR INSPECTION. |