Inspection History Details
Inspection Status: Approved
Inspection History: SITE - SEWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2007 | SITE - SEWER | Approved | IVRS - Inspection :* | |
| 10/02/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* VACUUM TESTING OF MANHOLES TODAY |
|
| 09/27/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. TEST PERFORMED: LOW PRESSURE AIR TEST VACUUM TEST MIRROR & MANDREL NEED TO SEE MANHOLE TESTS 2. 6" SDR 35 EXTENDED TO BLDG ONE OK SUBJECT TO TEST AND VERIFICATION OF GRADE. |
|
| 09/20/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. TRACER INSTALLED ON ALL HCS LATERALS. 2. 3 BASES SET 3. RECALL FOR MANHOLE STACKING. |
|
| 09/19/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. ALL HCS BRANCHES OFF OF MANHOLE TO TWO WAY CLEAN OUT TO BE TRACEABLE PER HB2256 2. RECALL O3057 WHEN GASES ARE BEING POURED. |
|
| 09/18/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. 8" SDR 35 FROM M.H #2 TO M.H #3 OK TO COVER SUBJECT TO TEST AT A LATER DATE, NEED VERIFICATION OF GRADE. 2. TWO BRANCHES OFF OF M.H #2 FOR COSMETIC BUILDING AND VEHICLE SALES EXTENDED PLUS OR MINUS 20 FROM MANHOLE. |
|
| 09/15/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. 8" SDR 35 FROM NEW CONNECTION TO MH #1 OK 8" SDR 35 STUBBED OUT OF M.H #1 AND TRANSITIONS TO 8" D.I.P FOR ABOUT TEN FEET -- BACK TO 8" SDR 35 TO M.H #2 OK TO COVER, SUBJECT TO VERIFICATION OF GRADE AND TEST AT A LATER DATE. |
|
| 09/14/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* PRECON MEETING MAVERICK UNDERGROUND T.L. ROOF ARCADIS ENGINEERING C.O.T 1. 8" D.I.P INSTALLED INTO EXISTING M.H OK NO CURB CUT AT THIS TIME 8" DIP EXTENDED 20' WITH PAD ADPT. TO 8" SDR 35 8" SDR 35 EXTEND APPROX. 20' OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TESTING AT A LATER DATE. |