Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/21/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 08/18/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. SHALL PROVIDE ROOF FLASHING AT PIPE PENETRATION THRU ROOF. 2. SYSTEM TO HAVE TEST ON ENTIRETY AT REINSPECTION. |
|
| 08/10/2006 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* GAS PRESSURE TEST SHALL INCLUDE ENTIRE SYSTEM BELOW GRADE SHUT OFF VALVE REQUIRES PERMANENT ACCESS, IF THIS IS IN A BAD LOCATION ALLOW A VALVE BOX THEN RELOCATE TO RISER. USE PRIMER AND TAPE ON ALL BELOW GRADE TOOL MARKS AND FITTINGS. YOUR SLEEVING IS NOT PROPERLY INSTALLED BUT IT IS NOT REQUIRED. EXPOSE GAS PIPING JOINTS FOR INSPECTION OF PIPE WRAPS. SUPPORT ROOFTOP PIPING NEAR FURNACE AND WH #2 PROVIDE OPERATING T&P RELIEF VALVES AND GRAVITY DRAIN TO EXTERIOR. INSTALL DIRT LEGS AT WHS NOTE WHS ARE FAIRLY NEW SECURE WH VENT PIPES W/GALV SCREWS. PROVIDE 1" CLEARANCE FROM COMBUSTIBLES. |