Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/27/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 07/24/2006 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 11.4 PSI RETEST PIPING AFTER INSTALLING AGA VALVES 1. PROVIDE TYPE B DOUBLE WALL FLUE VENT PIPING AND CAP, THROUGH CEILING AND TO TERMINATION POINT 1' ABOVE HIGH POINT OF ROOF. 2. SECURE VENT CONNECTOR W/GALV SHEETMETAL SCREWS 3. PROVIDE 1" CLEARANCE FROM COMBUSTIBLE MATERIALS 4. TERMINATE T&P OUTSIDE, 6" ABOVE GRADE 5. PROVIDE AGA GAS SHUT OFF VALVES 6. PROVIDE ELECTRICAL BONDING OF GAS PIPING 7. COMPLETE GAS PIPING AT FURNACE 8. CORRECT FURNACE FLUE PIPING - SAME REQUIREMENTES AS AT W.H. 9. SECURE/SUPPORT PIPING AT METER AND AT W.H |