Permit: T06PL00908

Parcel: 118040310

Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Date Description Inspector Results Comments
07/10/2006 PLUMBING - FINAL Approved
06/29/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
06/08/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
PROVIDE AN AIR PRESSURE TEST ON GAS PIPING.
AGA VALVES REQUIRED.
SHUT OFF VALVE SHALL BE LOCATED IN THE SAME ROOM AS THE APPLIANCE SERVED.
PROVIDE ELECTRICAL BONDING.
SUPPORT HORIZONTAL GAS PIPING AT EVERY 6'
WATER HEATER TEMPERATURE AND PRESSURE RELIEF VALVE SHALL GRAVITY DRAIN TO EXTERIOR W/APPROVED MATERIALS OR OBTAIN PETITION OF APPEAL FROM PERMIT COUNTER.
SECURE WH VENT CONNECTOR W/GALVANIZED SHEET METAL SCREWS.
PROVIDE 1" OF CLEARANCE BETWEEN B VENT AND COMBUSTIBLE MATERIALS.
SECURE PIPING AT FURNACE.
SUPPORT PIPING ON ROOF W/WEATHER RESISTANT PIPE SUPPORTS.
PIPING SHALL BE 1 1/2" ABOVE ROOF. ROOF PIPE PENETRATIONS SHALL HAVE FLASHINGS.
EXTEND WH AND FUR VENTS TO TWO FEET ABOVE COOLER.